Requirements

Case 1. Single family
Option 1: Energy and water
  1. Install an advanced energy monitoring system that meets the following requirements:
  • Meters must be permanently installed,
  • Record at intervals of 1 hour or less
  • Transmit data to the homeowner or occupant at a remote location (e.g, computer, in house display).
  • Separate energy usage information for at least four end uses such as space conditioning, water heating, and major plug loads.
  • Irrigation Meter. If an automatic in-ground irrigation system is part of the home project and the landscape irrigated area is larger than 1000 square feet, a sub-meter must be installed to monitor all irrigation system components.
  • AND/OR
    Option 2. Building Performance Partnership
    Homeowner must enroll in the USGBC Building Performance Partnership (BPP) for all applicable utility accounts, prior to submitting for LEED Certification/
    Case 2. Multi-family
    Option 1. Energy and water
    1. Install an advanced energy monitoring system for each unit that meets the following requirements:
    • Meters must be permanently installed,
    • Record at intervals of 1 hour or less
    • Transmit data to the homeowner or occupant at a remote location (e.g, computer, in house display).
    • Separate energy usage information for at least four end uses such as space conditioning, water heating, and major plug loads.
  • Irrigation Meter. If an automatic in-ground irrigation system is part of the home project and the landscape irrigated area is larger than 1000 square feet, a sub-meter must be installed to monitor all irrigation system components.
  • AND/OR
    Option 2. Building Performance Partnership
    Path 1: Whole-building master meter
    Building owner must enroll in the USGBC Building Performance Partnership (BPP) for all applicable utility accounts, prior to submitting for LEED Certification.
    OR
    Path 2. Individual unit meters
    At least 50% of unit owners or occupants must enroll in the USGBC Building Performance Partnership (BPP) for all applicable utility accounts, prior to submitting for LEED Certification. See all forum discussions about this credit »

    What does it cost?

    Cost estimates for this credit

    On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

    Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

    This information is also available in a full PDF download in The Cost of LEED v4 report.

    Learn more about The Cost of LEED v4 »

    Documentation toolkit

    The motherlode of cheat sheets

    LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

    USGBC logo

    © Copyright U.S. Green Building Council, Inc. All rights reserved.

    Requirements

    Case 1. Single family
    Option 1: Energy and water
    1. Install an advanced energy monitoring system that meets the following requirements:
    • Meters must be permanently installed,
    • Record at intervals of 1 hour or less
    • Transmit data to the homeowner or occupant at a remote location (e.g, computer, in house display).
    • Separate energy usage information for at least four end uses such as space conditioning, water heating, and major plug loads.
  • Irrigation Meter. If an automatic in-ground irrigation system is part of the home project and the landscape irrigated area is larger than 1000 square feet, a sub-meter must be installed to monitor all irrigation system components.
  • AND/OR
    Option 2. Building Performance Partnership
    Homeowner must enroll in the USGBC Building Performance Partnership (BPP) for all applicable utility accounts, prior to submitting for LEED Certification/
    Case 2. Multi-family
    Option 1. Energy and water
    1. Install an advanced energy monitoring system for each unit that meets the following requirements:
    • Meters must be permanently installed,
    • Record at intervals of 1 hour or less
    • Transmit data to the homeowner or occupant at a remote location (e.g, computer, in house display).
    • Separate energy usage information for at least four end uses such as space conditioning, water heating, and major plug loads.
  • Irrigation Meter. If an automatic in-ground irrigation system is part of the home project and the landscape irrigated area is larger than 1000 square feet, a sub-meter must be installed to monitor all irrigation system components.
  • AND/OR
    Option 2. Building Performance Partnership
    Path 1: Whole-building master meter
    Building owner must enroll in the USGBC Building Performance Partnership (BPP) for all applicable utility accounts, prior to submitting for LEED Certification.
    OR
    Path 2. Individual unit meters
    At least 50% of unit owners or occupants must enroll in the USGBC Building Performance Partnership (BPP) for all applicable utility accounts, prior to submitting for LEED Certification.