NC-2009 EAc5: Measurement and Verification

  • NC EAc5
  • Monitor energy—or more

    Measurement and verification (M&V) involves recording actual energy use over the course of occupancy, and comparing that data with the estimated energy use seen in the design. The M&V process ensures all systems are performing as specified and identifies any anomalies in equipment, operations procedures or user habits. In addition, an M&V plan can help reduce energy costs, assist with commissioning, and, over time, document and improve the efficiencies of energy conservation measures.

    M&V gives you a plan and a system to compare your project’s actual performance against design predictions. While M&V can be applied to a variety of metrics including water use and indoor environmental quality, this credit focuses only on energy performance. To earn it, you’ll need to develop an M&V plan, install devices to support the plan, and also have steps in place for corrective action. The credit requirements don’t tell you exactly what systems to monitor—that depends on your mechanical system design and what equipment you have installed. In general, you are expected to monitor energy from all systems or components that will provide data points for end uses identified in the energy model and that will help in the recalibration of the model. 

    What’s it cost?

    The cost of M&V varies a lot. Added costs come from designing and installing specific monitoring systems, including adding multiple meters and wiring. The cost is higher in larger and more complex buildings or those with multiple uses. The cost premium will be lower if your project already plans to include a Building Management System (BMS) or submeters to record usage data. If your building is small with a minimum set of uses, and needs only few meters to meet the credit, an M&V system might also be relatively affordable.

    For large buildings that have complex mechanical and electrical systems and that do not have a BMS, adding the equipment and systems needed to implement an M&V plan is likely to be cost-prohibitive. Some projects also find that Option B (see the Checklists tab) is particularly costly due to the requirements of added meters and wiring. 

    Is it worth it?

    Despite aiming high during design, LEED-certified buildings don’t always perform as well as expected. An M&V program will not only help building operators be aware of performance issues, it can locate the source of problems or poor assumptions, and provide a better overall understanding of the value of energy-saving strategies.

    To make the investment worth it, the owner must be committed to developing and implementing the M&V plan, analyzing and understanding the building’s performance, and acting on the results. The cost premium of M&V installation and operation is typically offset by long-term energy savings, but this is highly dependent on the building type as well as the owner’s willingness to make needed changes and upgrades. The credit is generally more applicable for larger commercial buildings than residential buildings since its cost benefits may not affect the developers directly. Residential buildings may also see less benefit because the building operator has little control over energy use by residents.

    Who does it?

    The “M&V provider” takes responsibility for developing the M&V plan. This role can be filled by the commissioning agent, energy modeler, mechanical engineer, project engineer, or a facilities manager.

    What’s the standard?

    The industry standard for M&V, both in the U.S. and internationally, is the International Performance Measurement and Verification Protocol (IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits.), owned by the nonprofit Efficiency Valuation Organization. LEED has singled out Volume III of the IPMVP guidance as the basis of its requirements. Several organizations have published M&V guidelines based on IPMVP. Among them are ASHRAE, the U.S. Department of Energy’s Federal Energy Management Program (FEMP), and some utilities and states that fund energy-efficiency projects. Some organizations with M&V standards offer guidance in writing M&V plans, including sample language. (See Resources for more information.)

    Commonly metered systems

    Although no specific metering is required for this credit, the following list outlines energy uses that are often included in the M&V plan (where applicable).

    • Lighting and lighting controls
    • Constant and Variable motors
    • VFDA variable frequency drive (VFD) is a device for for controlling the speed of a motor by controlling the frequency of the electrical power supplied to it. VFDs may be used to improve the efficiency of mechanical systems as well as comfort, because they use only as much power as needed, and can be adjusted continuously. Operations
    • VFD power use
    • Readings required for packaged equipment efficiency logging
    • HVAC loads
    • HVAC Systems, equipment, and controls
    • Hydronic heating efficiency
    • Domestic water heating efficiency
    • Building-related process energy systems and equipments
    • General water use
    • Process waterProcess water is used for industrial processes and building systems such as cooling towers, boilers, and chillers. It can also refer to water used in operational processes, such as dishwashing, clothes washing, and ice making. use
    • Process Refrigeration
    • Total Facility Gas usage metering
    • Total Facility Electricity usage

    Consider these questions:

    • Does the local utility offer any rebates or incentives for a BMS or sub-metering?
    • Are there any legal issues with third party sub-metering? Is third party sub-metering allowed by the local municipality or utility company?
    • What is the cost increase associated with a BMS and M&V plan?
    • Who will be the projects M&V provider (who will write the plan and perform the follow up tasks)? Who will train the operational staff to implement the M&V plan?
    • Are there any issues or limitations to including M&V maintenance and recording as part of the operational staff scope?
    • Would Option B or Option D be most appropriate for this project?
    • Will a BMS be incorporated in the building design?
    • What design constraints might be associated with including an M&V plan?
    • What would the scope of the system be? What end uses / systems are part of the project? How many sub-meters would the project need? If going for Option B, how many ECMs need to be isolated? If going for Option D, will an energy model be developed for EAc1 anyway?
    • What operational savings can the project team expect with an M&V plan?
    • What type of corrective action would be best for the project?
    • What is the level of precision desired for the M&V program?
    • What is the budget available?
    • What other energy awareness and reduction strategies are being considered or implemented?  (Educational Display, Fault Detection Diagnostics, Commisioning, etc.)  These strategies may have many synergies with M&V.

    FAQ's for EAc5

    How should we approach this credit for residential buildings where tenants are paying their own utilities?

    A measurement plan can include a sampling of units, and must include end uses. However, the metering does not have to be permanent. A short-term metering plan could be worked out with occupants in the units being sampled.

    Our project already includes a full direct digital control (DDC) system for HVAC. Does this satisfy the submetering requirements of this credit?

    No. DDC control points are not intended to measure energy consumption.

    Is the gas consumption of stoves, ovens, and etc. required under this point?

    It depends. This usage must be included in your models. If they are a significant energy user (say more than 5% of gas usage) then yes the energy use should be measured or derived. If the usage is small you might be able to make the case that you would not need to measure it.

    When is it applicable to go for option B instead of option D?

    Generally, if you have interactive energy conservation measures (ECMs) in new construction, you need to follow option D. Most new construction has interactive ECMs, and Option B is very rarely accepted by LEED reviewers for this reason.

    Is there a requirement to model baseline energy use as being 25% process loads?

    No. This is a consistent source of confusion and is not an ASHRAE or LEED requirement. You should always model the process loads as accurately as possible to reflect the actual building equipment and operation. If the baseline is less than the 25% default, simply note why that is the case.

    Does this credit specify how energy use should be measured?

    No. It can be a manual measurement, short-term trending device or permanent submeter. In certain situations an energy end use does not need to be "measured" at all but can be derived based on other data.

    What should the plan for corrective action contain?

    This part of the M&V Plan can't be very detailed since you do not yet know what needs to be done. What you will do depends upon the issues uncovered. In general the action plan simply identifies what you will do when deviations occur between the projected savings and the actual savings. Typically this involves identifying additional energy saving strategies in the facility and using the calibrated model, for example, to determine additional energy savings. The cost and savings of the additional energy saving measures should be summarized in the final M&V report. It's a good idea to indicate that the owner will be responsible for implementing these recommendations as budget and time allow.

Legend

  • Best Practices
  • Gotcha
  • Action Steps
  • Cost Tip

Pre-Design

Expand All

  • Consider incorporating a Building Management System (BMS) into the building. A BMS will streamline implementation of this credit, while offering other benefits.


  • Consider the impact of an M&V system on space requirements.  Keep in mind that a BMS will require additional space for monitors, wiring and sensors.


  • Consider the impact of an M&V program on mechanical system design requirements. Consider whether or not your mechanical system is capable of providing the necessary outputs for the BMS or monitoring system. The outputs are typically the energy usage recorded as kWh, Btus or therms for a given period of time. It may be an automated record kept by the BMS, or a metered reading on the equipment manually carried out at regular intervals. The specifics of the output metric and duration would be determined in the M&V plan and depend on the system installed. 

     


  • The “M&V provider” develops M&V plan. This role can be filled by the commissioning agent, energy modeler, mechanical engineer, project engineer, or a facilities manager. 

     


  • Contract with the M&V provider early in the process so that system components and recommendations can be implemented seamlessly into systems rather than becoming add-ons.

Schematic Design

Expand All

  • Discuss as a team whether M&V will contribute to the project’s goals for energy reduction and systems monitoring. Consider the project size, its complexity, and whether you plan to run a whole-building energy model. Also think about how the building is likely to be operated. If the system is not likely to be fully utilized, it may not be an appropriate investment.


  • Determine whether IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. Option B or Option D is most appropriate for the project design. (Option C, which was allowed in earlier versions of LEED, is not allowed, as it is considered less accurate, and doesn't allow for M&V of individual energy conservation measures.)

    • Option B is based on engineering calculations using metered data and is generally appropriate for smaller buildingswithout interactive systems. You will need to verify compliance with Option B for projects with more complex control systems. 
    • Option D uses calibrated whole-building energy simulations for both the baseline and design case and is generally appropriate for larger, more complex buildings where energy modeling has or will occur. 

  • Data to support calculations (Option B) or calibration of simulations (Option D) is taken from a combination of meters and sensors included in the building automation systems, and through temporary installation of additional sensors and data loggers as needed.

     


  • Energy savings is determined by comparing actual metered or measured energy use to the projected energy use of a baseline building under similar operating conditions.

    • Energy Savings = Projected Baseline Energy Use – Post-Construction Energy Use (actual metered energy use).
    • Post-Construction Energy Use is determined by utility metering or submetering, or by using an energy simulation model of the projected building.

  • Talk to the facility operations staff about the financial benefits and operational requirements of the M&V plan. Any energy savings achieved through M&V will depend on their participation.

     


  • Introduce the M&V program into the design early in the process, because it can affect the design of the mechanical and electrical systems as well as the BMS. There is also inherent value in having the design teams think about how the building will be operated.


  • Metering individual hotel rooms may not be feasible due to inconsistent occupancy and limited ability to control energy usage. If your hotel project includes M&V, you must track occupancy data based on daily sales records. Metering all common spaces can benefit operations, though it won’t be sufficient to earn the LEED credit. 


  • Multifamily residential buildings are required to submeter all apartments individually and to collect data from occupants. Usage information may be made available to the occupants and energy cost savings may be transferred in lease or sale contracts. 


  • Utility companies may provide incentives or rebates for submetering and BMS programs. For example, New York City provides $2,000 per meter for advanced master meter installation in affordable housing and $1,500 per meter for market-rate housing. Check with your local utility to see if they provide any rebates.


  • The cost of M&V varies significantly from one project to another. Projects will need to get project-specific bids based on their individual design needs. The usefulness and the cost of M&V plans are influenced by the following: 

    • Level of detail and effort associated with verifying post-construction conditions
    • Number and types of metering points
    • Duration and accuracy of metering activities
    • Number and complexity of dependent and independent variables that must be measured or determined on an ongoing basis
    • Availability of existing data collection systems such as energy management systems
    • Level of precision designed and specified into the system, and your confidence in the data analysis

  • An M&V program that is implemented throughout the life of the building will provide the highest return on investment.  Design your M&V program for use throughout the life of the building to provide the highest return on investment.


  • Option B: Energy Conservation Measure Isolation


  • Isolating and metering different ECMs, such as HVAC systems or lighting, can provide useful information on energy consumption and provide insight on energy reduction measures.


  • The cost implications for ECM isolation depend on how many meters are installed and the complexity of the systems being monitored. See the appendix in ASHRAE, Guideline 14 for estimating the cost of meters. If systems are easily isolated and don’t require many meters, this credit can be relatively cheap, with Option B being more cost-effective than Option D.


  • Option D: Calibrated Simulation


  • Sub-metering different use areas in mixed-use buildings, such as office and laboratory space, can offer insight into what energy reduction measures will be most appropriate for different use spaces. 


  • Option D is the best choice for projects with highly efficient building envelopes and efficient mechanical and electrical systems. 


  • Permanent submetering or a BMS is not necessary. Project teams can instead choose a combination of utility analysis, spot-metering and permanent metering. However, these other methods will not provide the detailed information that a BMS would and may not help projects determine energy problems or understand actual energy use. An M&V plan without a BMS is rare in large new construction projects, but smaller, single-occupancy buildings may find that packaged energy monitors or monthly utility bills can provide helpful feedback without the investment in a costly BMS.  


  • Most M&V programs submeter individual systems such as lighting, heating, and cooling. Plug loads are not always submetered individually, it is easiest to individually submeter larger items and subtract the totaled submeter number from the total building usage to get the estimated plug load number. 


  • An M&V program generally includes sensors—which measure the volume and rate of flow, watts of energy draw, temperature, length of time, and other variables—and a central processor—which stores the collected information and helps building managers interpret it. Building automation systems typically include the central processor needed for M&V, but not all of the sensors, or the additional programming to tally energy use and track patterns. Adding these pieces to a building automation system should be easy, though.


  • The cost implications of this credit vary from one project to the next. Costs will depend on the complexity of the meter and sub-metering system, the cost of energy modeling and calibration, the cost of commissioning, and the size and complexity of the building. The cost premium for M&V will be lower for projects that already include a BMS. 

    • For retrofits, costs of M&V average no more than 5% of the total project cost, studies show. 
    • For new construction, the combined cost of the installed equipment and the first year of monitoring is generally less than 1% of the total project cost for buildings larger than 150,000 square feet, and less than 1.5% for smaller buildings, according to studies.

  • The cost to create a M&V plan for Option D is influenced by the following, according to IPMVP:

    • Size and complexity of ECMs, systems or building
    • The degree of accuracy expected from your readings of measured energy use, compared with estimated energy use. A somewhat less accurate calculation will take less time.
    • Simulation software utilized and its associated complexity
    • Extent and sophistication of submetering

Design Development

Expand All

  •  Determine the extent of the M&V program based on the owner’s goals, the project type and function, and IPMVP requirements. M&V goals can be included in the Owner’s Project Requirements and Basis of Design documents for EAp1 and EAc3


  • The M&V provider reviews the project design to determine which systems and equipment will be metered, and also determines how many meters will be required


  • The M&V provider works with the MEP to verify that all systems are designed to allow metering and submetering. Meters must be capable of interfacing with the selected BMS or metering system. 


  • The MEP designs and specifies the appropriate submetering devices, controls and M&V system. The M&V provider verifies that the M&V program and systems are capable of providing the information required for the credit.


  • Permanent installation of water meters will allow easier monitoring of water consumption and savings. Although this is not required for LEED, water metering for graywater and rainwater systems is generally included in M&V plans, and monitoring general water use is also worthwhile, to verify projected savings. 


  • Adding a M&V program to the project after mechanical and electrical systems have been designed may be cost-prohibitive due to redesign costs.


  • Option B: Energy Conservation Measure Isolation


  • The M&V provider determines all of the ECMs that need isolation and verifies that these systems do not interact with any other ECM. 


  • The M&V provider works with the owner and MEP to determine the best solution for metering or submetering ECMs.


  • Option D: Calibrated Simulation


  • The M&V provider works with the owner to determine the best system for monitoring actual energy use.


  • Run a preliminary energy model. If an energy model is being developed for EAc1: Optimize Energy Performance, the model can be used as the energy use baseline for the M&V plan. Otherwise a new model may be run to determine the baseline energy use. The actual energy use will be compared to this baseline. 


  • The BMS should be set up to collect data that will allow fair comparison between actual and predicted energy use. For example, since weather patterns are factored into the energy model, the BMS should capture these, along with other parameters such as operating schedule, occupancy density, space use, and system settings. 


  • To achieve this credit under Option D, the M&V plan must be able to identify specific building performance issues. A BMS or submetering will be able to build this capacity into the system.


  • The Whole Building Calibration Simulation requires information about the instruments that enable the project to monitor the categories listed in the IPMVP. 


  • The question of which systems need to be monitored is building-specific and is not prescribed by the credit requirements. 


  • Total energy consumption of the building must be tracked, along with any variables that may influence energy consumption. For example, in a hotel you would need to track occupancy. 


  • Projects must verify the savings of the efficiency measures. If individual metering capacity is not built into the project, the project must demonstrate some other firm commitment to obtaining this data. This requirement can be accomplished by providing a copy of the contract for data collection by a third party of individual meters. 

Construction Documents

Expand All

  • The M&V provider writes the M&V plan. If possible, involve the facility’s operational staff in writing the plan. The plan should lay out the measurement and response protocol. The M&V plan must define the following:

    • Baseline energy use
    • Post-construction energy use
    • Any adjustments that should be made to the baseline energy use

  • The industry standard for M&V plans, both in the U.S. and internationally, is the International Performance Measurement and Verification Protocol (IPMVP), owned by the nonprofit Efficiency Valuation Organization. LEED has singled out Volume III of the IPMVP guidance as the basis of its requirements, and several organizations have published M&V guidelines based on IPMVP. Among them are the American Society of Heating, Refrigerating, and Air-Conditioning Engineers (ASHRAE); the U.S. Department of Energy’s Federal Energy Management Program (FEMP); and some utilities and states that fund energy-efficiency projects. Some organizations with M&V standards offer guidance in writing M&V plans, including sample language.


  • Coordinate with the mechanical and electrical engineers to verify that the control devices will be able to provide the information needed for credit compliance.


  • The owner’s goals and IPMVP guidelines should drive the M&V plan, which should specify which systems are to be sub-metered and which are being spot metered, and how. The plan also explains how the energy end use is being predicted and measured, and how the M&V information will be used, such as adjusting building operations to reduce energy use. The plan shall also include a section on corrective action that will take place if the baseline energy use and the post-construction energy use vary greatly. 


  • The plan establishes who is responsible for managing the process during operations and for taking corrective action. The plan also establishes how long the monitoring will continue. 


  • The M&V provider demonstrates through a narrative that the M&V plan will be able to verify actual energy use. For energy systems that are not addressed in the M&V plan you will need to provide a detailed reason for exclusion in the narrative. 


  • The M&V plan should define the actions that will be taken by the facility manager to investigate the cause of any discrepancies found and correct any malfunctioning equipment. If goals are not met, or if unexpected performance occurs, the M&V systems will provide useful feedback in tracking the source of problems.


  • Variable loads such as dimming controls can be profiled with short-term measurements that determine a load value pegged against another variable point that can be measured or accurately estimated over time. ECMs have to be metered to obtain actual savings. Variable loads like dimming controls can be measured only by metering them first at full power and then at low power. Measure and plot the power use at various dimming points at consistent time intervals. 


  • Option B: Energy Conservation Measure Isolation


  • Determine the baseline energy use for the ECMs.

     


  •  The projected baseline energy use can be determined using energy efficiency standards or guidelines.


  •  Option D: Calibrated Simulation

     


  • Run a final energy model that reflects all of the as-designed energy-efficiency measures.  


  • The projected baseline energy use is calculated by an energy model during the design phase. All ECMs are removed from the model and this energy data becomes the baseline to determine energy savings when compared to the actual energy use. According to Option D of IPMVP III, the model must be calibrated so it is ready to be used after one year of data collection.


  • It is easiest to calibrate the as-built energy simulation software if submetering devices correlate with the breakdown of the energy usage in the energy model. 


  •  Where applicable, the M&V plan should specify submetering sensor locations. Define the specific sensors with their location and sampling rates. In the plan, define the required energy model output and how measured data will be compared to the energy model. Also define how loads are arranged and grouped in electric panels; mixing power, lighting and HVAC equipment loads within individual panels is not recommended. 

     

     

Construction

Expand All

  • The M&V submetering devices or BMS are installed and commissioned to verify functional accuracy.

     


  • Installation of the M&V system should be fairly straightforward. Depending on the system and the experience of the subcontractors, however, specialized contractors may be needed.


  • Option D: Calibrated Simulation 


  • Verify that the whole-building simulation model matches the as-built design. 

Operations & Maintenance

Expand All

  • The M&V plan is implemented for at least the first year of building operations.


  • Ensure that appropriate personnel are trained to optimize the system to its greatest potential.


  • Track and archive trending data with utility metering and energy submetering systems required by the M&V plan.


  • Provide a yearly summary report that identifies energy performance issues and corrective actions.


  • If there are discrepancies between projected energy use and actual use, identify the cause and follow the M&V plan for corrective action. Discrepancies may result from inaccuracies in the simulation model, actual building use that differs from anticipated occupancy, improperly functioning equipment, and switches and controls not being properly calibrated. 


  • Meters and submeters should be recalibrated periodically according to manufacturers’ recommendations.


  • Encourage the operations team to focus on running the building at optimal efficiency. 


  • Record any post-construction upgrades or changes to operations and maintenance in order to best understand post-construction energy use. 


  • A 5%–10% discrepancy between the baseline energy use and the post-construction energy use may account for operational changes in a good energy model. However, a 25% discrepancy would not be out of the ordinary. 


  • The payback period for M&V programs depends on the initial cost of additional meters and whether the program identifies inefficiencies that wouldn’t have been found otherwise. Some fixes may be substantial and will pay for the metering system. After the BMS or metering system has been installed, the true return depends on the commitment of the owner and operational staff. Because M&V monitors actual building operation over time, M&V procedures can lead to valuable operational savings by uncovering building system design, installation, and control issues not caught by commissioning. 


  • M&V systems require continuous energy use and staff attention. One of the larger costs associated with this credit is the time needed by staff to read, interpret, and act on feedback provided by the M&V system. Although more expensive to install, a complex building or a building with multi-tenant spaces can benefit financially from an integrated computerized BMS that assists in day-to-day management. 


  • Option B: Energy Conservation Measure Isolation


  • The facilities manager or M&V provider compares the baseline energy use of the ECMs to the post-construction energy use.


  • The ECM usage can be tracked with a simple spreadsheet and does not require complicated calculations or modeling.


  • Option D: Calibrated Simulation


  • Set up the BMS to provide monthly reports as required by the M&V plan, if applicable. 


  • Perform a calibrated building energy simulation model that reflects actual occupancy and weather, after the first year’s energy usage data becomes available. The energy modeler performs the calibrated simulation with the assistance of the M&V provider. 


  • The calibrated energy simulation gives the owner and facility operator a true picture of savings from the ECMs instead of the predicted savings from the energy model developed during design. A simulation model developed during design makes a lot of assumptions on occupancy patterns, set points and weather. A calibrated energy model replaces those assumptions with real data while accommodating unforeseen program changes. If the actual results are greater than 10% from the predicted ones, compare the differences between the assumptions and the actual settings. Calibration is a great learning opportunity for the modeler to verify those assumptions with actual data. After the first year, you do not need to recalibrate the model, instead using energy usage from utility bills to compare against energy usage from previous years. The calibrated model is compared to the actual energy consumption rates and changes need to be made to the model until acceptable calibration is achieved. After all calibration adjustments have been made to the as-built energy model the same changes need to be made to the baseline energy model. 


  • Energy savings is verified by either comparing the calibrated as-built model to the calibrated baseline model, or by comparing the calibrated baseline energy use to the actual metered energy use.


  • Twelve months of data from the metered categories is used to calibrate the computer simulation model. The M&V plan shall demonstrate the ability to identify specific problem areas if discrepancies exist between the modeled and metered data. When calibrating the as-built energy model, weather patterns must be reflected. You may be able to obtain this through the BMS. Calibration changes will also include occupancy and operational adjustments to reflect actual usage.


  • Calibration of the energy model will add a small cost on top of the cost of the baseline as-built energy model.

  • USGBC

    Excerpted from LEED 2009 for New Construction and Major Renovations

    EA Credit 5: Measurement and verification

    3 Points

    Intent

    To provide for the ongoing accountability of building energy consumption over time.

    Requirements

    Option 1

    Develop and implement a measurement and verification (M&V) plan consistent with Option D: Calibrated Simulation (Savings Estimation Method 2), as specified in the International Performance Measurement & Verification Protocol (IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits.), Volume III: Concepts and Options for Determining Energy Savings in New Construction, April 2003.

    The M&V period must cover at least 1 year of postconstruction occupancy.

    Provide a process for corrective action if the results of the M&V plan indicate that energy savings are not being achieved.

    OR

    Option 2

    Develop and implement a measurement and verification (M&V) plan consistent with Option B: Energy Conservation Measure Isolation, as specified in the International Performance Measurement & Verification Protocol (IPMVP) Volume III: Concepts and Options for Determining Energy Savings in New Construction, April, 2003.

    The M&V period must cover at least 1 year of postconstruction occupancy.

    Provide a process for corrective action if the results of the M&V plan indicate that energy savings are not being achieved.

    OR

    Option 3. Third Party Data Source (1 point)

    Meet MPR 6 through compliance Option 1: Energy and Water Data Release Form. Projects must register an account in ENERGY STAR’s Portfolio Manager tool and share the project file with the USGBC master account.

    Potential Technologies & Strategies

    Develop an M&V plan to evaluate building and/or energy system performance. Characterize the building and/or energy systems through energy simulation or engineering analysis. Install the necessary metering equipment to measure energy use. Track performance by comparing predicted performance to actual performance, broken down by component or system as appropriate. Evaluate energy efficiency by comparing actual performance to baseline performance.

    While the IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. describes specific actions for verifying savings associated with energy conservation measures (ECMs) and strategies, this LEED credit expands upon typical IPMVP M&V objectives. Measurement & verification activities should not necessarily be confined to energy systems where ECMs or energy conservation strategies have been implemented. The IPMVP provides guidance on M&V strategies and their appropriate applications for various situations. These strategies should be used in conjunction with monitoring and trend logging of significant energy systems to provide for the ongoing accountability of building energy performance.

    For the corrective action process, consider installing diagnostics within the control system to alert the staff when equipment is not being optimally operated. Conditions that might warrant alarms to alert staff could include:

    • Leaking valves in the cooling and heating coils within air handling units;
    • Missed economizerAn economizer is a device used to make building systems more energy efficient. Examples include HVAC enthalpy controls, which are based on humidity and temperature. opportunities (e.g., faulty economizer damper controls) ;
    • Software and manual overrides allowing equipment to operate 24 hours a day/7 days a week;
    • Equipment operation during unusual circumstances (e.g., boiler on when outside air temperature is above 65 °F).

    Besides control diagnostics, consider employing retro-commissioning services or dedicating staff to investigate increases in energy usage (such a staff member is usually a resource conservation manager — see http://www.energy.state.or.us/rcm/rcmhm.htm for additional information).

Other

Efficiency Valuation Organization (EVO) Blog

M&V blog that is a place where the community can raise and discuss issues that arise in the practice of valuing efficiency projects. 

Technical Guides

IPMVP Volume I and III

IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. is the standard upon which the LEED M&V requirements are based. Use these documents should be used in designing the M&V system and plan. 


Applications Team, Energy-Efficiency Design Applications: Measurement & Verification Documents

This website provides a list of resources to help teams implement an M&V program.


M&V Guidelines: Measurement and Verification for Federal Energy Projects

These M&V guidelines are written for federal buildings but could be helpful for many projects. 


ASHRAE Guidelines 14-2004

ASHRAE provides technical guidelines for designing an M&V plan. This document can assist project teams in designing and implementing the M&V systems and plan.  

Organizations

The Energy Valuation Organization and the Association of Energy Engineers

The Energy Valuation Organization, in conjunction with the Association of Energy Engineers, offers an M&V professional certification program. The Association of Energy Engineers holds training seminars for those preparing to take the certification exam and anyone else interested in learning the fundamentals of M&V and working with IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits..  

Publications

Energy Management Handbook, By Wayne C. Turner, Steve Doty

Chapter 27 covers Measurement and Verification of Energy Savings and has some very useful information from the history of M&V, including various methods and equipment. 


Environmental Building News, June 2006.

This article discusses the usefulness of M&V, including examples of problems that M&V systems have been able to identify. 

Software Tools

WATERGY Software

NOTE: WATERGY is not currently available, but may be again in the future.

WATERGY is a spreadsheet model that uses water and energy relationship assumptions to analyze the potential of water savings and associated energy savings. 

Web Tools

USGBC Building Performance Partnership

USGBC’s Building Performance Partnership (BPP) engages commercial and residential LEED building owners and managers in an effort to optimize the performance of buildings through data collection, analysis and action. This partnership among USGBC and the thousands of LEED project owners will result in the population of a comprehensive green building performance database, enable standardization of reporting metrics and analytics, and establish new performance benchmarks. USGBC’s BPP participants are eligible for annual performance reports, report cards and real-time data interfaces to aid in their building performance goals. Together, USGBC and BPP participants will transform the way the world views building operations.

Template for M&V Plan

Option D: Calibrated Simulation

The Measurement and Verification (M&V) plan template shown here is based on Option D: Calibrated Simulation.

M&V Plan Sample

Option D: Calibrated Simulation

This Measurement and Verification (M&V) plan sample follows Option D: Calibrated Simulation.

Construction Submittal

HardhatDocumentation for this credit is part of the Construction Phase submittal.

LEED Online Forms: NC-2009 EA

The following links take you to the public, informational versions of the dynamic LEED Online forms for each NC-2009 EA credit. You'll need to fill out the live versions of these forms on LEED Online for each credit you hope to earn.

Version 4 forms (newest):

Version 3 forms:

These links are posted by LEEDuser with USGBC's permission. USGBC has certain usage restrictsions for these forms; for more information, visit LEED Online and click "Sample Forms Download."

189 Comments

0
0
Billy Ryan
Jul 03 2014
Guest
5 Thumbs Up

LEED NC 2009 EAc5 Measurement and Verification

I am currently training and researching in order to become involved in the M&V process for various new construction buildings within the near future.

The area I am having a particular difficult time finding reference material for is determining meter locations. I have found some best practice guides and have perused the ASHRAE guideline 14 book, as well as read a significant amount of IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. volume III. I am having difficulty finding anything with specific reference on how to determine submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system). locations based off of a single line diagram, or other something similar.

If anyone might have some advice, I would greatly appreciate it.

1
1
0
Marcus Sheffer LEED Fellow, 7group Jul 03 2014 LEEDuser Expert 40096 Thumbs Up

For LEED projects you are following Option D, Calibrated Simulation. In simple terms you measure the data you will need to enable you to calibrate the energy model with the actual energy use. You are gathering data for each of the significant energy end uses (lighting, heating, cooling, fans, plug loads, etc.) since you cannot calibrate a model based on a comparison of annual fuel use alone. This could involve energy meters for some or all of the end uses. Putting an energy meter on every end use can become costly so quite often monitoring points are used to gather data (like run time for a fan motor) and then energy use is derived instead of directly measured. Sometimes energy use for some end uses can be derived by subtraction (for example in a packaged roof top unit you can meter the whole unit, measure fan run time, derive the fan energy use and subtract it to determine cooling energy use). Sometimes energy use can be derived by taking spot measurements or with short term trending devices and using that data to derive energy use.

Our goal on every M&V job is to figure out the least expensive way to gather the data we need on each project. Quite often the way we gather data will vary significantly from project to project. I do not think that you will find what you are seeking in a reference. The documents you read outline the principles to follow - you then have to apply them.

Post a Reply
0
0
Jim Gardler Manager Cx Concord Engineering
Jun 09 2014
LEEDuser Member
2 Thumbs Up

LEED NC 2009 EAc5 Measurement and Verification

We have developed a M&V plan for a mixed use Multi tenant high rise with commercial space in the building with the International Performance Measurement and Verification Protocol (IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits.) as the framework for this plan. IPMVP Volume III 2003, Option D, Calibration Simulation, has been selected as the method of M&V for this project. This entails the use of an energy simulation model to estimate the annual building energy consumption of the facility. We feel we have a good plan moving forward however there has been concern from the our client and team as to whether or not USGBC will approve of our approach. I know that this approval does not happen until the project is fully completed but is there any recommendation on getting some guidance from USGBC on approach and published data for certified projects with specifics on points?
Thank you in advance for any guidance

1
1
0
Marcus Sheffer LEED Fellow, 7group Jun 16 2014 LEEDuser Expert 40096 Thumbs Up

I am not aware of any pre-review or guidance from USGBC beyond what is in the referenced materials. Review of the entire Plan is beyond a LEED InterpretationLEED Interpretations are official answers to technical inquiries about implementing LEED on a project. They help people understand how their projects can meet LEED requirements and provide clarity on existing options. LEED Interpretations are to be used by any project certifying under an applicable rating system. All project teams are required to adhere to all LEED Interpretations posted before their registration date. This also applies to other addenda. Adherence to rulings posted after a project registers is optional, but strongly encouraged. LEED Interpretations are published in a searchable database at usgbc.org. but you could try to summarize the approach and seek approval that way.

There are consultants who provide such pre-review services (full disclosure - we are one of many who do so and I apologize for the blatant self-serving suggestion but I do think this may be your best option). It should only take an hour or so to review the plan and offer recommendations for improvement.

You could also search for copies of M&V Plans that have been approved in the past to see if your approach is close.

Not sure what you mean by "specifics on points"?

Basically the reviewers are looking to make sure you have a good solid understanding of the IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits., that you are collecting sufficient data to calibrate the energy model, that you understand what it takes to calibrate a model, and that the Plan addresses all of the items in Section 3.2.

Post a Reply
0
0
Sasha Peters
May 28 2014
LEEDuser Member
23 Thumbs Up

EA Cr5: Measurement & Verification for projects wherein Option D

The query is with reference to achieving EA Cr5: Measurement & Verification for projects wherein Option D and Option B of IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. Vol.III is not possible.

In lieu of same, please confirm if in such case can any project achieve 1 credit only by compliance to MPR6 requirements of sharing the whole building energy & water usage data. Earlier version of LEED template did have provision of this as option 3. Please confirm if this scenario still prevails.

The project is ready to share the Energy and water performance via Energy Star Portfolio manager but currently have only main meters installed to measure the total building energy and water usage and do not have sub-meters in place to measure the utility level consumption. If answer to the above query is yes, please clarify the following relevant to the compliance of MPR6 and thereby EA Cr5 requirements.

• Can provision of only main meters for total energy and water consumption suffice the requirement of MPR6? As energy profile can be created in portfolio manager only using the total energy and water consumption values, the need for additional energy sub-meters could be avoided thereby reducing the initial cost for the client.

• In case provision of sub-meters are mandatory for MPR6 and sub-meters are not installed during the project submissions to LEED, please provide a specific timeline, if any, within which the sub-meters should be installed on-site.

1
1
0
Marcus Sheffer LEED Fellow, 7group May 28 2014 LEEDuser Expert 40096 Thumbs Up

Yes you can still earn one point for Option a in MPR 6.

No submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system). required.

Post a Reply
0
0
FABIO VIERO Head of Sustainability Manens-Tifs s.p.a.
Apr 19 2014
LEEDuser Member
403 Thumbs Up

Exception to DES

Hi,

I'm now working on a group project certification based on three buildings.

The HVAC System has a central cooling system that serves only the three buildings.

The central cooling system is located within the leed boundary of the group certification.

According to http://www.usgbc.org/Docs/Archive/General/Docs7671.pdf may I exclude to consider the central cooling system as a DES?
(in other words, can I assume that my case is equivalent to what described at page 6 of the document linked above: "Exception: When several buildings are grouped as part of a single LEED project, including a central plant building, the central plant is defined as a DES only if it currently serves or is expected to serve other buildings not within the LEED project boundaries for the project"?)

Thanks!

1
2
0
Marcus Sheffer LEED Fellow, 7group Apr 23 2014 LEEDuser Expert 40096 Thumbs Up

Are you wanting to exclude something (like the central plant building) from your LEED certification? Excluding something raises overall questions about the LEED submission beyond just the modeling issue.

Are you modeling all three buildings in one model or each building separately?

Have you seen the new campus guidance from USGBC issued April 1, 2014?

Based on the excerpt you provided from the DESv2 it sounds like the plant can't be considered as a DES since it does not serve other building outside the LEED boundary.

2
2
0
FABIO VIERO Head of Sustainability, Manens-Tifs s.p.a. Apr 23 2014 LEEDuser Member 403 Thumbs Up

Marcus,

thank you for you reply.

Yes, I know the last update of LEED Campus Guidance.

I include this central plant in the LEED certification.

I think to model the three buildings separately (it seems to be too complex to model them together for the software's capacity).

Many thanks.

Fabio

Post a Reply
0
0
FABIO VIERO Head of Sustainability Manens-Tifs s.p.a.
Apr 19 2014
LEEDuser Member
403 Thumbs Up

DES and EAc5

Hi,
I'm now working on a project under LEED certification, according to NC v2009.
This project is served by a DES: it is more than 50.000 sqf of GFA, in which the DES supplies energy for more than 20% of the project building’s annual energy cost and we are going to pursue points under EAc1, using the performance path.

According to the document you can find at http://www.usgbc.org/Docs/Archive/General/Docs7671.pdf, it seems that M&V Plan should include the full accounting of upstream DES whole-system energy.

Performance and consumption information of whole DES are not available, because the public provider does not share technical details about the plant.

Consider that this plant serves an entire city.

How we can pursue this credit?

Thanks!

1
2
0
Marcus Sheffer LEED Fellow, 7group Apr 23 2014 LEEDuser Expert 40096 Thumbs Up

Ciao Fabio!

All you need to do for the upstream equipmentUpstream equipment consists of all heating or cooling systems, equipment, and controls that are associated with a district energy system but are not part of the project building's thermal connection or do not interface with the district energy system. It includes the central energy plant and all transmission and distribution equipment associated with transporting the thermal energy to the project building and site. is confirm the energy modeling values you used relative to this plant. Seems odd that a "public" system would not share any technical details. I assume you used the default values for the plant in your model. If the information remains impossible to obtain I would ask the provider to send me a letter indicating that they will not provide the information needed. This gives you proof that you can't get the information. I would then write the M&V Plan in a way that allows me to account for these variables the best way that I can.

Good luck.

2
2
0
FABIO VIERO Head of Sustainability, Manens-Tifs s.p.a. Apr 23 2014 LEEDuser Member 403 Thumbs Up

Marcus,

thanks!
Fabio

Post a Reply
0
0
David Hubka Director - Operations Transwestern Sustainability Services
Apr 17 2014
LEEDuser Expert
661 Thumbs Up

EAc5, Option #3 = MPR #6

Why are project teams awarded a point for following the requirements of a Minimum Program Requirement?

I am not complaining, I love free points!... just curious.

Any feedback is greatly appreciated.
thanks.

1
3
0
Marcus Sheffer LEED Fellow, 7group Apr 17 2014 LEEDuser Expert 40096 Thumbs Up

The MPR is a requirement for most project but not all. There are loopholes being closed by making it a prerequisite in v4.

USGBC wants the data to see how LEED projects are performing.

And the other options for M&V are commonly confused and often not even implemented. Rather give a point for data than 3 points for a worthless plan.

Those are the ones off the top of my head.

2
3
0
Christopher Schaffner Principal & Founder, The Green Engineer, LLP Apr 17 2014 LEEDuser Expert 7238 Thumbs Up

Actually, you only get the point if you sign the project up for Portfolio Manager and set up automatic reporting. So you are going beyond the MPR, which just asks for reporting "if" you have meters.

3
3
0
David Hubka Director - Operations, Transwestern Sustainability Services Apr 23 2014 LEEDuser Expert 661 Thumbs Up

thanks for the responses, that makes sense.

Post a Reply
0
0
Catalina Caballero Sustainability Coordinator JALRW Eng. Group Inc.
Apr 01 2014
LEEDuser Member
2021 Thumbs Up

Mixed Use Building Residential + Commercial

We are working in a project for which we will be pursuing LEED NCv2009. It is a mixed use (residential and commercial) building. However the commercial areas will be treated as a shell for future tenants. The owner wants to proceed everything as part of one rating (NC) therefore I was wondering if there is submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system). required for future tenants, or if it can be satisfied by having a letter from the owner saying how future tenants will treat their spaces to keep the certification in place?

Thanks.

1
1
0
Marcus Sheffer LEED Fellow, 7group Apr 02 2014 LEEDuser Expert 40096 Thumbs Up

There are no submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system). requirements at all for this credit. The submetering of tenant spaces by fuel type will likely not produce much useful information for the M&V Plan. A letter from the owner would not be sufficient to document any potential outcomes related to the tenant spaces. The only documentation acceptable for changes would be a lease agreement that requires the tenant to make a certain change of follow a particular performance metric.

You will need to account for how you will calibrate the energy model for the entire building including the tenant spaces within the M&V Plan. During design you should be thinking about how you will be gathering the data you need to calibrate the energy model from the whole building including the tenant spaces. In order to implement the M&V plan the tenant spaces would likely need to be occupied.

Post a Reply
0
0
Catalina Caballero Sustainability Coordinator JALRW Eng. Group Inc.
Mar 31 2014
LEEDuser Member
2021 Thumbs Up

Measurement and Verification for two building campus (metering)

Hello. We are currently working on a project for which the LEED boundary includes everything in the campus like a bus maintenance facility and offices, except an office/garage hybrid building next to this one. However there are two chillers and two boilers that serve both buildings. We are having an issue defining how to sub-meter this for the M&V. We will be providing temp sensors and flow sensors connected to a BMS at the AHUs corresponding to the LEED boundary areas. But my main question would be, does the sub-meter have to be assigned per parameter or output of the energy model to be calibrated or does it have to be per energy source? The reason I'm asking is because we have some circuits that are together (lets say some plug loads and some lighting) and pretty difficult to sub-meter by function within the circuit. What type of report is required after calibration. Is there an example?

Thanks.

1
3
0
Marcus Sheffer LEED Fellow, 7group Apr 01 2014 LEEDuser Expert 40096 Thumbs Up

In order to calibrate an energy model you need to measure energy use by end use. Fuel type can work if there is only one or two end uses associated with it. This does not mean that you need permanently installed submeters in every case. We once did calibration on a small library with no submeters. The measurements were all spot measurements and short term trending meters.

For example, in the case where the lighting and plug loads are on the same circuit you could submeter it and then figure out a way to determine the lighting portion (perhaps spot measurements of the power draw of the lighting fixtures attached to that circuit) and subtract that from the total to separate the end uses. Use the lighting data to calibrate the lighting energy use and the plug load data to calibrate the plug load energy use.

In order to effectively calibrate an energy model you need to calibrate it by end use on a monthly basis.

Effective submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system). goes back to designing the layout of the panel boards so this process should start early in design.

2
3
0
Catalina Caballero Sustainability Coordinator, JALRW Eng. Group Inc. Apr 01 2014 LEEDuser Member 2021 Thumbs Up

Do you know whwere can we find an example of the report to be submitted by the end of the measurement and verification period?

Thanks.

3
3
0
Marcus Sheffer LEED Fellow, 7group Apr 02 2014 LEEDuser Expert 40096 Thumbs Up

Your can find a couple of examples of our M&V reports on our web site at http://www.sevengroup.com/r-project-reports/energy/mv-reports/

You could also try - http://www.evo-world.org/index.php?lang=en

Post a Reply
0
0
Renee Shirey
Mar 21 2014
LEEDuser Member
2828 Thumbs Up

Confused by Third Party reporting tequirement of Option 3

I would love some insight on why, if going for Option 3, the whole-building water and energy usage data reporting MUST be done by a Third Party Data Source, vs. the actual Owner? What is gained by this, besides a consultant getting paid for something the owner/client could do on their own? Please help.

1
1
0
Marcus Sheffer LEED Fellow, 7group Mar 23 2014 LEEDuser Expert 40096 Thumbs Up

This does not mean you have to hire a consultant. The easiest way to do this and the way that enables you to earn a point for reporting the data is Option 1. The owner just agrees to enter the data in Portfolio Manager.

Post a Reply
0
0
Eamon Geary Sustainability Director - Facilities Michael Baker Jr, Inc.
Dec 18 2013
LEEDuser Member
630 Thumbs Up

Implementing the M&V Plan

I have a project seeking this credit where our MEP subconsultant is writing the M&V Plan and the Owner is implementing the M&V Plan. The Owner will likely hire a facilities manager however I am trying to define the qualifications required to implement the M&V Plan. I have been unsuccessful at finding anything in writing to give to my owner. Any help would be appreciated.

1
1
0
Marcus Sheffer LEED Fellow, 7group Dec 18 2013 LEEDuser Expert 40096 Thumbs Up

The critical qualifications are those of the person/firm that will be responsible for calibrating the energy model. The typical owner/facility manager generally does have this expertise. The typical facility manager can gather data (sometimes with some training) and perform some of the tasks associated with implementing the Plan.

Post a Reply
0
0
Eamon Geary Sustainability Director - Facilities Michael Baker Jr, Inc.
Dec 11 2013
LEEDuser Member
630 Thumbs Up

Initial energy model required for M&V?

I am working on a large campus project. We are planning on obtaining EA 5 for all eight facilities on the campus. However, we are not doing energy models for all eight facilities. We are obtaining credit EA 1 for five of the buildings using the Prescriptive Compliance Path: Option 2 and the Prescriptive Compliance Path: Option 3. SInce we don't have an initial energy model to 're-calibrate' for these five facilities I would like to know if we still obtain this credit? Would the authority responsible for validating the M&V process after occupancy be responsible for creating a model? Does our M&V plan need to indicate this?

1
3
0
Marcus Sheffer LEED Fellow, 7group Dec 11 2013 LEEDuser Expert 40096 Thumbs Up

You could still get the credit by following Option D and creating an energy model. This would have to be clearly spelled out in the M&V Plan and part of the plan is always to identify the responsible parties for all of the M&V tasks.

Unless you can make the case that this approach adds value to the projects, it strikes me that attempting to do so is simply a point hunting exercise. I would concentrate on the value proposition and only follow Option 1 if it makes sense to do so. Otherwise consider Option 3.

2
3
0
David Eldridge Project Manager, Grumman/Butkus Associates Feb 10 2014 LEEDuser Member 459 Thumbs Up

Marcus, Option B for ECMEnergy conservation measures are installations or modifications of equipment or systems intended to reduce energy use and costs. isolation might also be technically possible...although it may be difficult depending on the mix of ECMs, and whether any interact. (And what doesn't interact with the HVAC system?)

I don't think Option D is point hunting necessarily if the client really wants to verify the performance. It would be an example of unfortunate timing, since the energy models could have been used for so much more if completed earlier instead of post-construction.

Option 3 for one point is going to look very attractive to your client if the cost of full M&V (and all of this modeling) is too high.

3
3
0
Marcus Sheffer LEED Fellow, 7group Feb 10 2014 LEEDuser Expert 40096 Thumbs Up

I have not seen a green building yet where Option B would work but I am sure it is possible.

Sounds like we agree that any IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. M&V effort is only worth it if it adds value. IMO it is point hunting if it does not add value beyond the accumulation of those points. If it does add value then it is all good.

Post a Reply
0
0
Omar Katanani
Nov 13 2013
LEEDuser Member
7563 Thumbs Up

VAV System with Reheat

Dear All,

We have a project installing a VAVVariable Air Volume (VAV) is an HVAC conservation feature that supplies varying quantities of conditioned (heated or cooled) air to different parts of a building according to the heating and cooling needs of those specific areas. air conditioning system with electrical reheat boxes in each zone.

The current design assigns energy submeters combining both the electrical reheat with the small equipment power.

My query is: do we need to monitor / submeter the electrical reheat separately, given that it is not as significant as the total heating consumption from the building boilers?

Thanks!

1
1
0
Marcus Sheffer LEED Fellow, 7group Nov 13 2013 LEEDuser Expert 40096 Thumbs Up

You are actually not required to monitor or submeterSubmetering is used to determine the proportion of energy or water use within a building attributable to specific end uses such as tenant spaces, or subsystems such as the heating component of an HVAC system. anything by the IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits..

Can you accurately calibrate the model with the information you are currently gathering? Can you gather or derive the data another way, without a submeter? What is "not as significant"? If the energy use is very small for both the electric reheat and the small equipment power then you would need to justify that the usage is not significant (which you would define in your M&V Plan). Relative significance is not the issue, overall significance is the issue.

So you need to answer your own question. Do you need that data to calibrate your model?

Post a Reply
0
0
Radwa Amin Mechanical and control Engineer Hill International-North Africa
Sep 30 2013
LEEDuser Member
168 Thumbs Up

Option D

Hello there,

My project team wants to add the M&V however we are facing physical constraints on adding digital meters for all the electro-mechanical systems.

Could we count on the logical measurement via the BMS system monitoring to performance instead of having real accurate measurement?

Thank you.

1
1
0
Marcus Sheffer LEED Fellow, 7group Sep 30 2013 LEEDuser Expert 40096 Thumbs Up

You are not required to have any submeters by the IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits..

Measurements from the BMS may work. Just be sure that the M&V Plan spells out how these will translate to a measurement of energy use for each of the major energy end uses.

Post a Reply
0
0
Thomas Huang
Sep 27 2013
Guest
30 Thumbs Up

More option D vs option B

Thank you for this very helpful forum. I have read every comment on EAc5 as I prepare to submit our first M&V plan. Under NC2009, I am pursuing M&V but I am looking at significant additional cost to "recalibrate" the model. I am looking to make the argument that actual measured data is more effective than recalibrating the model.

My questions are:

1. Does option D require recalibrating the model or is it sufficient to take measurements and compare to the original modeling predictions to highlight deficiencies? sect. 4.5.7. of IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. says you must calibrate both baseline and asbuilt models, 4.5.8 method 2 says you can subtract metered asbuilt energy from a calibrated baseline energy model to determine savings. This would give actual savings which is what we are after right?

2. If option D does require calibration of the model, I am considering option B but I see the comments that option B is rarely accepted for NC. Can we avoid the issue with interdependent ECMEnergy conservation measures are installations or modifications of equipment or systems intended to reduce energy use and costs.'s if we just measure everything such that interdependencies are quantified? Our manufacturing processes require intensive monitoring and control (+/-0.1degF and %RH) so most points are existing with portable instruments to cover gaps. For example, we stream all chiller, pump, fan data and trend flows and delta T’s so isolating ECM’s to validate a metric like kW/ton is readily available. This way I could compare work in (kW) to work out (btuh to kW) and assume that the remaining converts to heat to the ambient space.

Interested to hear whether you think this is viable with GBCI. Tks so much for any guidance you would be willing to offer.

1
2
0
Marcus Sheffer LEED Fellow, 7group Sep 30 2013 LEEDuser Expert 40096 Thumbs Up

1. You must calibrate the model. It is not sufficient to compare the modeling results to the actual. Either approach is acceptable. The thing to keep in mind is that the purpose of the IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. is to produce verified energy savings. For new construction that is comparison to an Appendix G baseline.

2. The basic issue with Option B is the degree of interactive energy efficiency strategies. If you can isolate each one individually you may be able to make the case for using it. In my experience this is virtually impossible (or far more difficult) to do for each one without an energy model.

2
2
0
Thomas Huang Oct 02 2013 Guest 30 Thumbs Up

Got it, tks very much Marcus

Post a Reply
0
0
Soo young No FCA construction
Sep 05 2013
LEEDuser Member
252 Thumbs Up

Energy Star's energy report

According to EA5 Measure and verification, required 1 year of energy usage report.
But in PI from 1: Minimum Program Requirement (PIf1-1), required for duration of five years.
Is it under same Energy Building registration?
Do we do five years or one year?
Anyone know?

1
3
0
Marcus Sheffer LEED Fellow, 7group Sep 05 2013 LEEDuser Expert 40096 Thumbs Up

EAc5 Option 1 or 2 requires one year of data and a significant effort to implement a M&V Plan.

EAc5 Option 3 requires providing 5 years of data.

2
3
0
Soo young No FCA construction Sep 05 2013 LEEDuser Member 252 Thumbs Up

After completing PI form with five year commitment, we have picked option 1 for the EAc5. Is that OK?
I guess we have to go with five years,right???
Thank you.

3
3
0
Marcus Sheffer LEED Fellow, 7group Sep 05 2013 LEEDuser Expert 40096 Thumbs Up

Yep Option 1 within the PIf4 form is the one which earns one point.

You commit to providing data for five years.

Post a Reply
0
0
Candice Rogers Paladin, Inc
Aug 26 2013
LEEDuser Member
218 Thumbs Up

M&V Template - End Use Metering Table

Hello -

We're submitting for M&V under LEEDv2009. We're going with Option D - Calibrated Simulation. Our energy model did not use the performance path. The template form is the Beta version (and I don't believe that the team will update the form versions as we've already got credits completed for our Construction Phase submission).

I'm confused on the first table in the template. We have our End Use and Proposed Energy Consumption. My question is: "How do I complete the table for 'Metered Energy Use' when we haven't started to perform the work in the M&V plan?" Am I misinterpreting the value that we are supposed to input into this table?

Many thanks-
Candice Rogers

1
1
0
Candice Rogers Paladin, Inc Aug 26 2013 LEEDuser Member 218 Thumbs Up

Hello -

Nevermind. I figured out how to upgrade the form...it looks like it won't upgrade all forms in the project.

Thank you -
Candice

Post a Reply
0
0
Alex Parella Architect_LEED AP
Jul 03 2013
LEEDuser Member
61 Thumbs Up

M&V option D. certification timing

When using Option D, should we wait till the end of the 1 year monitoring to obtain the credit and, therefore, the final building certification? Or would be enough to submit the M&V plan and get the compromise to monitor and fulfill it, like in Option B?
Thanks in advance

1
4
0
Marcus Sheffer LEED Fellow, 7group Jul 03 2013 LEEDuser Expert 40096 Thumbs Up

The credit achievement is based on the M&V Plan you submit. You do not need to wait until the plan has been fully implemented to obtain the credit and earn certification.

With that said by creating the plan you are saying that you will implement it and USGBC takes you at your word. Unfortunately far too many projects have not implemented their M&V Plan based on some of the follow up studies on LEED projects.

Option B rarely works for new construction/major renovation projects.

2
4
0
Alex Parella Architect_LEED AP Jul 04 2013 LEEDuser Member 61 Thumbs Up

Thank you very much, Marcus

3
4
0
Rudolph Carneiro HVAC consultant, Sustentech Oct 30 2013 Guest 546 Thumbs Up

Is the USGBC doing anything about enforcing the activities in the M&V Plan? I ask because it is much more compelling (financially) for a building owner to not install any metering infrastructure (seperate circuitry, Building management system with datalogging capability, etc..) then to just have a consultant create an elaborate measurement and verification plan that includes spot measurement and trending for all the building systems.

4
4
0
Marcus Sheffer LEED Fellow, 7group Oct 30 2013 LEEDuser Expert 40096 Thumbs Up

Not sure which way to take your question so I will address both ways.

You are not planning to implement the Plan - Let your conscious be your guide. Personally if I write a M&V Plan I will not submit it unless it will be implemented. To do otherwise is simply dishonest no matter the level of enforcement.

You are planning to implement the Plan - In my experience if it is a very small project with very simple HVAC systems then it is cheaper overall to forgo the submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system).. If it is a larger project the cost of the submetering will pay for itself in avoided labor. So it comes down to a balance between the metering costs versus the labor required to gather the data without it.

Post a Reply
0
0
Genko Ganev President MV Automation
Jun 28 2013
Guest
50 Thumbs Up

Option #3 is added to EAc5 M&V

I would like to find out what are the requirements for achieving EAc5 - Option #3?
Where can I find information to read on MPR #6? and
What is :" Option 1 in Pl Form1?

Thank you very much

1
1
0
Marcus Sheffer LEED Fellow, 7group Jun 28 2013 LEEDuser Expert 40096 Thumbs Up

You agree to provide to USGBC 5 years of energy data. Most commonly this would be provided through a Portfolio Manager account (part of US EPA Energy Star). You can view the LEED Online forms on USGBC's web site. PIf1 is the MPRs.

http://www.usgbc.org/sampleforms

Post a Reply
0
0
Andrew Ellsworth Ellsworth Building Portfolio Services
Jun 20 2013
LEEDuser Member
127 Thumbs Up

M&V Versus Ongoing Sub-Metering & Monitoring

I am glad to have a forum like LEEDuser to ask this question, since this has mystified me for many years. The M&V activities described by the credit language seem to me to do more benefit to the engineer than to the building owner. In essence, this credit is written to validate and calibrate the energy model, though it doesn't seem to have a direct focus on maximizing building and system efficiency. In my opinion, the real benefits of a sub-metering system are to:

1) Identify equipment that is malfunctioning: running for too long, not functioning at all, drawing energy at higher demands than usual.
2) Make effective use of maintenance staff by addressing small problems before they become big problems.
3) Decrease the likelihood of equipment failure as a result of neglect and the associated costs of new equipment and interruption of the activities of the building.

Am I missing something about the value of this LEED credit that is somehow larger than long-term energy monitoring?

Additionally, in the past I have written M&V plans geared towards long-term energy monitoring, and not validation of the energy model. These have generally been accepted, as we tend emphasize the human capacity in place to make use of the data and deal with exceptions. We have made general nods towards IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. Option D, but don't closely align to it. We use the first year of data as the baseline for comparison, as the systems are new and recently commissioned. Subsequent years/months are compared to those in the baseline to identify problems and exceptions.

However, in this new era of strict adherence to LEED language, I worry that this approach may no longer fly. Also, projects we have worked on focus on electricity consumption, and not gas or water. Does anyone have any guidance on how these are being reviewed and what exactly is considered acceptable these days?

Any insights would be appreciated.

Andrew

1
1
0
Marcus Sheffer LEED Fellow, 7group Jun 20 2013 LEEDuser Expert 40096 Thumbs Up

Many people have been highly confused about the fundamental purpose of this credit. In certain respects the credit intent is not in full alignment with the intent of the referenced standard. In LEED v4 the IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. portion of the credit was removed and the new credit will be more in alignment with your understanding.

The one thing I did not see in your post is the fundamental purpose of the IPMVP upon which credit compliance is based. The IPMVP was created to create a uniform set of methodologies to verify predicted energy savings. Some owners benefit from this pursuit, some do not.

The benefits of submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system). are related to this credit but permanently installed submetering systems are not a requirement to comply with IPMVP. So if you submeter then yes there are operational benefits as you describe.

M&V Plans have been accepted that focus on the credit intent rather than IPMVP Option D compliance. It is not possible to say whether your approach would be accepted or not without thoroughly reviewing the details. In general is you are submetering the major energy end uses and have a monitoring and corrective action plan in place you can make the case that you comply with the credit intent even if you do not necessarily comply with the IPMVP Option D.

If you are following Option D then you will need to demonstrate in the Plan a detailed description of how you are going to gather the data one would need to calibrate the energy model, how you are going to go about calibrating the energy model and reconcile it with the actual utility bills to verify savings and what are going to do if the savings turn out to be less than predicted.

Post a Reply
0
0
Catalina Caballero Sustainability Coordinator JALRW Eng. Group Inc.
Jun 03 2013
LEEDuser Member
2021 Thumbs Up

Cooling Tower Submetering

Under the reference guide, it is requiring for process waterProcess water is used for industrial processes and building systems such as cooling towers, boilers, and chillers. It can also refer to water used in operational processes, such as dishwashing, clothes washing, and ice making. to be submetered, which according to the glossary involves cooling tower water, boilers and chillers, but if the cooling tower is serving several tenant, how can it be measured or segreated to be measured?

1
1
0
Marcus Sheffer LEED Fellow, 7group Jun 03 2013 LEEDuser Expert 40096 Thumbs Up

I could not find a reference to process waterProcess water is used for industrial processes and building systems such as cooling towers, boilers, and chillers. It can also refer to water used in operational processes, such as dishwashing, clothes washing, and ice making. in EAc5 in the Reference Guide. Is it in an addenda?

Post a Reply
0
0
Alicia Silva CEO Revitaliza consultores
May 03 2013
LEEDuser Member
1389 Thumbs Up

Sub-metering in Option D

Marcus Sheffer posted some months ago in this credit:

"You will need to calibrate the model by energy end use on a monthly (and annual) basis.
[...]
Yes you would need to separate out the electric end uses in order to calibrate the model. Whole building metered data is not sufficient."

HOWEVER

I am reading the IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits., page 18, Table 2:

"How Savings Are Calculated:
[...]
Energy use simulation, calibrated with hourly or monthly UTILITY BILL data. (Energy end use metering MAY be used to help refine input data.)"

Therefore, sub-metering does NOT appear to be mandatory for credit compliance, since sub-metering MAY be used to help refine input data.

I am glad to have different insights to this issue.

GH

1
6
0
Alicia Silva CEO, Revitaliza consultores May 03 2013 LEEDuser Member 1389 Thumbs Up

In addition, quoting the IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. Vol III, Concepts and Practices for Determining Energy Savings in New Construction, Part I, page 18:

"Option D Involves of computer simulation of whole building energy use. The Post-Construction Energy Use is determined by utility metering and/OR submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system). or by using an energy simulation model of the as-built building calibrated to metered energy use data."

GH

2
6
0
Jatuwat Varodompun Dr, Green Building Soultion May 03 2013 LEEDuser Member 1087 Thumbs Up

I think I was the one who also asked Marcus regarding this issue. I think the reviewer will look for the method of how we can reach the end-use energy data. Some of them might require only runtime record if the equipment consume constant power. I used to create IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits. plan this way and try to find the solution for obtain the data for each end-use (fan, chiller, pump, light, etc.). Yes, the submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system). is not mandatory if you can find to solution to extract the end-use from the whole.

3
6
0
Marcus Sheffer LEED Fellow, 7group May 03 2013 LEEDuser Expert 40096 Thumbs Up

Good to see someone reading the IPMVPThe International Performance Measurement and Verification Protocol (IPMVP) provides best-practice protocol for measurement and verification of new construction. This standard is referenced in LEED's measurement and verification credits.! I am not sure too many folks submitting M&V Plans have done so.

Let me see if I can explain the the rationale for needing energy end use data. First of all I do not believe I ever said that projects had to install submeters. There are several ways to get energy end use data and submeteringSubmetering is used to determine the proportion of energy use within a building attributable to specific end uses or subsystems (e.g., the heating subsystem of an HVAC system). is just one of them. Sometimes it is not even actual energy use data as it could be data you would use to calculate energy use. You are correct that submeters or any direct measurements of energy use by end use are not required.

You will still need to calibrate your energy model by energy end use and have a data gathering plan in place to enable it. If you just calibrated to the monthly utility data by fuel type you could very easily be over predicting one end use and under predicting another and on balance the result may "appear" to match but it doesn't. You will find that it is virtually impossible to get each month to match within a reasonable range. When it does not match then you will need to have some kind of energy end use data to figure out the discrepancy. So the M&V Plan must include a methodology to gather the data needed by energy end use. It cannot be an afterthought that you will figure out after the results do not match. I can guarantee that the monthly data will not match in all cases so you are going to need some additional data. I think anyone who has calibrated an energy model would attest to this fact.

Recently we gathered some whole building data for a project we modeled that was an all electric building. Our model was within 6 kWhA kilowatt-hour is a unit of work or energy, measured as 1 kilowatt (1,000 watts) of power expended for 1 hour. One kWh is equivalent to 3,412 Btu. in the annual total energy consumption. Pretty good huh? Well it turns out we over predicted heating and under predicted cooling and on balance we got lucky. Even if each month was within range we would not have a calibrated model.

Unfortunately the language in the IPMVP is often a bit vague. It sets out broad goals and lets you figure out how to get there. Based on first hand experience I can tell you that you can't calibrate to the utility bills without calibrating to energy end use. Another way to think about it is to focus on the outcome. The energy model basically needs to be fully reflective of the way the actual building operates in order to be accurately calibrated. Without any energy end use data I would suggest that it would be impossible to do so.

Now the question becomes do we need to measure or meter each energy end use? Probably not. Very small ones that do not have a big impact on the overall energy use can be estimated. Maybe HVAC can be lumped together instead of trying to break out fans, pumps, heating and cooling. Some end uses could be derived from subtraction. This starts to get very project specific and how you do it depends on many factors.

If you can make the case in your M&V Plan that you can accurately calibrate the energy model without any energy end use data I would like to read how you will do it. If you think it through you will find that it is not possible unless you have clairvoyant energy modelers!

4
6
0
Alicia Silva CEO, Revitaliza consultores May 06 2013 LEEDuser Member 1389 Thumbs Up

Marcus, thanks for your comment. I think it was very clarifying.
Then, the key point is how to calibrate the model by energy end use. We have some ideas:

1.Sub-metering
2.Utility bills (in big projects utility bills could be differentiated by end use)
3.Data loggers that record energy use in different circuits according to the modeler's needs. Data could be recorded over a 7-day period (for example) and estimate the rest of the month.

Is this correct?
Someone could bring up more options?

5
6
0
Marcus Sheffer LEED Fellow, 7group May 06 2013 LEEDuser Expert 40096 Thumbs Up

Yes you are correct. Here are some others.

You can take spot measurements and use that data to calculate the energy use. For example, if I know that the lighting is a constant load (i.e. always on) and the schedule is consistent (on at the same time, off at the same time) I could use a clamp on meter, measure the wattage of each fixture type, count the fixtures and do the math.

I mentioned subtraction before. For example, if you meter lighting, hot water and HVAC you could derive plug loads by subtracting the submetered data from the utility meter data.

Some information can be obtained through interviews with operational staff. Things like occupancy and schedules are often obtained this way.

Commissioning activities often yield useful information what can be used in calibration.

Hand calculations could be used to verify very small constant loads if necessary.

And do not forget to calibrate the weather file to reflect the actual weather during the M&V period.

6
6
0
Alicia Silva CEO, Revitaliza consultores May 06 2013 LEEDuser Member 1389 Thumbs Up

Absolutely helpful. Thanks again and I hope this helped other project teams to earn this credit.

GH

Post a Reply
0
0
Gustav Alfaro Mechanical Engineer
May 02 2013
LEEDuser Member
116 Thumbs Up

Defining the baseline

Hi to all:

Please help me to clarify how the baseline model is defined for the M&V plan, it is clear that for the "actual case" the proposed model created for the EAc1 must be calibrated based on energy bills and measured performance during one year; but how is defined the baseline mode for comparision purposes? Should it be the proposed model delivered for EAc1? Should it be the baseline model delivered for EAc1? Should it be the proposed model delivered for EAc1 substracting the ECMEnergy conservation measures are installations or modifications of equipment or systems intended to reduce energy use and costs. implemented during the design and construction?

Thank you a lot for your comments

1
5
0
Marcus Sheffer LEED Fellow, 7group May 02 2013 LEEDuser Expert 40096 Thumbs Up

You basically take the calibrated model of the building and use that to create another Appendix G baseline model. This is your calibrated baseline for comparison.

So the adjusted schedules, utility rates, occupancy, etc. that must be identical are taken from the calibrated model and applied to the Appendix G baseline model.

2
5
0
Gustav Alfaro Mechanical Engineer May 02 2013 LEEDuser Member 116 Thumbs Up

Thank you for your soon feedback. What you indicate is what I understood but the Reference Guide says "Calibration is achieved by adjusting the energy simulation model to reflect actual operating conditions and parameters. Next, the conservations measures are removed from the model to define the baseline..." so, this sentence is kind of confusing because it seems that, for instance, if one of the conservation measures was to insulate the walls, then in the EAc5 baseline models the walls should appear without insulation (removing the conservation measures). Id appreciate if you can clarify further.

3
5
0
Marcus Sheffer LEED Fellow, 7group May 02 2013 LEEDuser Expert 40096 Thumbs Up

They mean that you should take the level of wall insulation from what you have in your building back down to the code minimum insulation value. An Appendix G baseline does just that.

4
5
0
Gustav Alfaro Mechanical Engineer May 02 2013 LEEDuser Member 116 Thumbs Up

Thank you Marcus

5
5
0
Thiago Bondini Jul 05 2013 LEEDuser Member 285 Thumbs Up

I mistakenly assumed that the baseline energy model for this credit would be the as-built simulation used to document compliance with EAp2 and EAc1 rather than the appendix G model. It made sense to me to compare actual energy use to projected energy use but I suppose in the end you end up with the same information.
Thank you.

Post a Reply
0
0
Lauren Fakhoury Research Assistant Sustainable Design Consulting, LLC
Apr 26 2013
Guest
1155 Thumbs Up

M&V Plan for Residential Project

Hi all,
I'm working on a residential project where the tenants do NOT pay their utility bills. The units are being individually sub-metered but the electric company does not provide a breakup per unit, instead a total bill goes to management. We are working to find out if a breakdown is possible, but in the meantime does anyone have experience creating an M&V plan for this type of project? Thanks.

1
3
0
Marcus Sheffer LEED Fellow, 7group Apr 26 2013 LEEDuser Expert 40096 Thumbs Up

We have explored the possibility of doing so on a couple residential projects. The complexity involved in gathering the necessary data is far higher with these types of projects and as a result each time we explored it it was abandoned as too difficult and expensive.

If you do pursue it I would suggest that perhaps you consider a sampling protocol for the units to keep the cost down.

2
3
0
Lauren Fakhoury Research Assistant, Sustainable Design Consulting, LLC Apr 29 2013 Guest 1155 Thumbs Up

Thanks, Marcus. I should clarify - the owner is willing to bear the cost. How do we get the information from the service provider if the tenant isn't responsible?

Thank you.

More replies to "M&V Plan for Residential Project" on next page...

Start a new LEED comment thread

Jul 28 2014
Type the characters you see in this picture. (verify using audio)
Type the characters you see in the picture above; if you can't read them, submit the form and a new image will be generated. Not case sensitive.

Copyright 2014 – BuildingGreen, Inc.