NC-2009 EAp2: Minimum Energy Performance

  • NC EAp2 Credit Req's Diagram
  • Check updated requirements

    USGBC's membership approved an update to LEED 2009 effective April 8, 2016. The update only affects LEED 2009 projects registered on or after that date.

    Project teams will be required to earn a minimum of four points in EAc1, effectively making EAp2 more stringent. The referenced energy standard and modeling requirements are not changed. Buildings falling under the proposed change can use the same methodologies and referenced standards, but will need to earn additional points in order to achieve certification. 

    The intent of the change is to bring LEED 2009 energy requirements more up to date, as LEED 2009 continues to be the predominant LEED rating system, even though the more up-to-date LEED v4 has also become available.

    Beyond code compliance, but doable

    This prerequisite is a big one, not only because it’s required for all projects, but also because it feeds directly into EAc1: Optimize Energy Performance, where about a fifth of the total available points in LEED are at stake. Master these minimum requirements, and you can use the same compliance path as in EAp2 to earning points.

    You won’t earn the prerequisite by accident, though. Although “energy efficiency” is on everyone’s lips, the mandatory and performance-based requirements for EAp2 go beyond code compliance in most places. That said, there is nothing to stop you from meeting the requirements with a reasonable amount of effort, and the environmental benefits as well as the operational cost savings are significant.

    Most projects start by choosing which of the three available compliance paths to follow. We’ll look at them each in turn.

    Option 1: Energy modeling

    Option 1 alone gives you access to all of the points available through EAc1, and offers the most flexibility in giving you credit for innovative designs.

    First, you need to meet the mandatory requirements of ASHRAE 90.1-2007 for all major components, including the envelope, HVAC, lighting, and domestic hot water. ASHRAE 90.1 has had some changes and new mandatory requirements since the 2004 version, which was referenced on previous LEED systems, so be sure to review the standard carefully.

    Cost of changeEnergy efficiency is an area where it behooves project teams to start early and work together to maximize savings. Playing catch-up later on can be costly.Second, you need to demonstrate a 10% savings (5% for existing buildings) for your designed building compared with a baseline case meeting the minimum requirements of ASHRAE 90.1 (or Title 24-2005, Part 6 for California projects). You do this by creating a computer model following rules described in Appendix G of ASHRAE 90.1.

    Computer modeling offers the following key advantages:

    • It can be used to provide feedback on your design both early on, and as the design progresses, so it’s best to use in this way rather than simply demonstrating compliance.
    • It can help your team focus on the most cost-effective efficiency strategies, by plugging in different options and seeing the results.
    • If your building is unconventional or complex in design, an energy model is the best way to account for that.

    Your building type may not have a choice—you may have to follow this path, because both Options 2 and 3 are prescriptive compliance paths that are only available to specific building types and sizes.

    However, if your building type and size allow, and you don’t want to embark on the complex process of computer modeling, which also requires expert assistance from a modeler or from a member of the mechanical engineer’s team, the prescriptive compliance paths are a good way to earn the prerequisite simply by following a checklist.

    Solar shadingPassive design strategies such as shading to reduce solar heat gain are the most cost-effective ways to improve energy performance.Note, however, that when you get to EAc1, there are a lot fewer points on the table for the prescriptive paths, and that you have to follow each prescriptive requirement. These paths also require more collaboration and focus early on in design than you might think. The design team must work together to integrate all of the prescriptive requirements, and Option 3 even requires documentation of certain design processes.

    Option 2: ASHRAE Advanced Energy Design Guides

    The Advanced Energy Design Guides are published by ASHRAE for office, warehouse, and retail projects less than 20,000 ft2—so if you don’t fall into one of those categories, you’re not eligible for this path.

    These guides outline strategies to reduce energy use by 30% from 2001 levels, or an amount equivalent to approximately 10%–14% reduction from ASHRAE 90.1-2007. If you choose this compliance path, become familiar with the list of prescriptive requirements and commit to meeting all of them.

    Option 3: Advanced Buildings Core Performance Guide

    The Core Performance Guide path is a good option if all of the following are true:

    • your project is smaller than 100,000 ft2,
    • you cannot pursue Option 2 because there is not an ASHRAE guide for the building type,
    • your project is not a healthcare facility, lab, or warehouse,
    • and you would rather not commit to the energy modeling required for Option 1.

    Comply with all requirements within Sections 1 and 2 of the guide. If you choose this path, become familiar with the list of prescriptive requirements and commit to meeting them. Also note that it’s not just a list of prescriptive requirements, but a prescribed process for achieving energy efficiency goals. You must demonstrate that you considered a couple of alternate designs, for example, and that certain team meetings were held.

    Reduce energy loads first

    Energy efficiency offers a clear combination of environmental benefit and benefit to the owner through reduced operational expenses, and potentially reduced first costs, if you’re able to reduce the size and complexity of your HVAC system with a more efficient envelope.

    High-tech HVAC systems, and onsite renewable energy generation are often signature components of green buildings, but consider these strategies more “icing” on the cake, rather than a place to start. Start with building orientation and passive design features first. Also look at envelope design, such as energy-efficient windows, walls and roof, before looking at HVAC and plug loads. A poorly designed envelope with a high-tech HVAC system is not, on the whole, efficient or cost-effective. 

    District energy systems

    Projects connected to district energy systems will not be able to utilize the system efficiencies of the base plant to demonstrate compliance with the prerequisite. They can plan on benefiting from these systems under EAc1, however.

    Look for incentives

    Focusing on energy efficiency and renewable energy generation can seem to add costs to a project, but there are a variety of utility-provided, as well as state, and federal incentives available to offset those premiums. (See Resources.)

  • FAQs for EAp2

    Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

    Ideally if the software you are using cannot model a technology directly then seek a published workaround related to your software. If you can't find a published workaround then model it as you think it should be modeled and explain how you have modeled it in the preliminary LEED submission.

    A portion of our building envelope is historic. Can we exclude it from our model?

    No, not if it is part of the LEED project. However, there is an exemption for existing building envelopes in Appendix G that allow you to model the existing condition in the baseline so you do not pay a penalty.

    For an existing building, do I need to rotate the model?

    No, not for an existing building.

    Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the process load?

    You must model accurately. Since you don't have enough savings in the building energy, find savings in the process. Either you will be able to demonstrate that compared to a conventional baseline the process being installed into the factory is demonstrably better than "similar newly constructed facilities," allowing you to claim some savings, or the owner needs to install some energy-saving measures into the process to get the project the rest of the way there. Either option can be difficult, but not impossible.

    Account for process load reductions through the exceptional calculation method. A baseline must be established based on standard practice for the process in your location. Any claim of energy savings needs a thorough narrative explaining the baseline and the strategy for energy savings along with an explanation of how the savings were calculated.

    Our process load is higher than 25%. Do we have to justify that?

    It is common to have a 80%–90% process load in a manufacturing facility. The 25% default in LEED is based on office buildings. If you think your load is lower than 25%, it is recommended that you explain why in a short narrative. It is also recommended to briefly explain it if your load is 25% exactly, since that level commonly reveals that the process loads were not accurately represented.

    Do the required savings for this prerequisite (and credit) need to come only from building energy, or also process loads?

    The energy savings are based on the whole building energy use—building and process. LEED does not stipulate exactly where they come from.

    Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

    For LEED 2009 you'll need touse 90.1-2007. There were some significant changes in 90.1-2010—too many to account for in your LEED review, and your project would also have a much harder time demonstrating the same percentage energy savings.

    Our project doesn't have enough energy savings to earn the prerequisite. Can we get there by incorporating onsite renewables?

    Yes according to LEED, although it is not recommended as a best practice, and it is usually more cost-effective to invest in energy savings in the building.

    Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

    You can assume exterior lighting savings for canopies against the baseline, but not the shading effects of canopies.

    The project is built on a site with existing exterior lighting installed. How should this be accounted for?

    If exterior lighting is present on the project site, consider it as a constant in both energy model cases.

    Can mezzanines open to floors below be excluded from the energy model?

    Any conditioned area must be included in the energy model.

    How do I provide a zip code for an international location?

    The Energy Star portion of the form does not apply to international projects.

    For a project outside the U.S., how do I determine the climate zone?

    Use the tables and definitions provided in 90.1 Appendix B to determine an equivalent ASHRAE climate zone.

    For a project outside the U.S., how do I determine the Target Finder score?

    International projects are not required to enter a Target Finder score. Target Finder is based on U.S. energy use data.

    Do hotel rooms need automatic light shut-off control?

    For Section 9.4.1.1c, a manual control device would be sufficient to comply with mandatory provisions.

    How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

    Submitting these forms is not common; however, it can be beneficial if you are applying for any exceptions.

    The Section 9 space-by-space method does not include residential space types. What should I use?

    Use the building area method.

    Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

    Although there is no formal list of approved simulation tools, there are a few requirements per G2.2.1, including the ability of the program to provide hourly simulation for 8760 hours per year, and model ten or more thermal zones, which PHPP does not meet.

    Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

    The automated Trace 700 report provides less information than is requested by the Section 1.4 tables spreadsheet. The Section 1.4 tables spreadsheet must be completed.

    Which baseline HVAC system do I use if my building has no heating or air conditioning?

    Assign HVAC systems as per Appendix-G and Section 6 but set thermostatic setpointsSetpoints are normal operating ranges for building systems and indoor environmental quality. When the building systems are outside of their normal operating range, action is taken by the building operator or automation system. out of range so that systems never turn on.

    Our project has a diesel backup generator. Should we include it in our energy model?

    If it is only used for backup and not for regular use such as peak shaving—no.

    Can SHGC be higher in the proposed than in the baseline model?

    SHGC is not a mandatory provision so it is available for trade-off and can be higher than the baseline.

    Do I need to justify the electrical and fuel rates I am using in my model?

    You generally wouldn't need to upload any documentation, but particularly for a non-U.S. project, it may help to provide a short narrative about what they are based on.

Legend

  • Best Practices
  • Gotcha
  • Action Steps
  • Cost Tip

Pre-Design

Expand All

  • Discuss your project’s energy performance objectives, along with how those are shaping design decisions, with the owner. Record energy targets in the Owners Project Requirements (OPR) for the commissioning credits EAp1 and EAc3


  • You won’t earn this prerequisite by accident. The energy efficiency requirements here are typically much more stringent than local codes, so plan on giving it special attention with your team, including leadership from the owner. 


  • Consider stating goals in terms of minimum efficiency levels and specific payback periods. For example: “Our goal is to exceed a 20% reduction from ASHRAE 90.1, with all efficiency measures having a payback period of 10 years or less.”


  • Develop a precedent for energy targets by conducting research on similar building types and using the EPA’s Target Finder program. (See Resources.)


  • For Option 1 only, you will need to comply with the mandatory requirements of ASHRAE 90.1-2007, to bring your project to the minimum level of performance. The ASHRAE 90.1-2007 User’s Manual is a great resource, with illustrated examples of solutions for meeting the requirements.


  • ASHRAE 90.1-2007 has some additional requirements compared with 2004. Read through the standard for a complete update. The following are some samples. 

    • All exterior walls must be installed with rigid insulation of the spans across all floors. This can be accomplished by placing the insulation outside the air barrier. 
    • All exterior doors must be tested for maximum air leakage rate. 
    • All spaces must have independent lighting controls. 
    • Occupancy sensors must be installed in some spaces.
    • The minimum efficiency level of specific mechanical equipment has been raised.  

  • The prerequisite’s energy-reduction target of 10% is not common practice and is considered beyond code compliance. 


  • ClerestoryIndirect sunlight delievered through clerestories like this helps reduce lighting loads as well as cooling loads. Photo – YRG Sustainability, Project – Cooper Union, New York A poorly designed envelope with a high-tech HVAC system is not, on the whole, efficient or cost-effective. Start with building orientation and passive design features first when looking for energy efficiency. Also look at envelope design, such as energy-efficient windows, walls and roof, before looking at HVAC and plug loads. HVAC may also be a good place to improve performance with more efficient equipment, but first reducing loads with smaller equipment can lead to even greater operational and upfront savings. A poorly designed envelope with a high-tech HVAC system is not, on the whole, efficient or cost-effective. 


  • Don’t plan on using onsite renewable energy generation (see EAc2) to make your building energy-efficient. It is almost always more cost-effective to make an efficient building, and then to add renewables like photovoltaics as the “icing” on the cake.


  • Some rules of thumb to reduce energy use are:

    • Program similar spaces together to reduce distribution losses 
    • Use a window-to-wall ratio below 40%, on average
    • Use a window-to-wall ratio below 20% on east and west sides, to reduce low-angle solar gain, and glare; 
    • Reduce direct solar gain with solar shades or building geometry and orientation
    • Distribute heating and cooling loads uniformly throughout all facades for a smaller system size. 
    • Design a tight and well-insulated building envelope to reduce the heating load and improve HVAC performance
    • Use right-sized and efficient heating and cooling systems
    • Consider onsite renewable energy generation.

  • Choosing your compliance path


  • Find the best credit compliance path based on your building type and energy-efficiency targets. Use the following considerations, noting that some projects are more suited to a prescriptive approach than others. 


  • Option 1: Whole Building Energy Simulation requires estimating the energy use of the whole building over a calendar year, using methodology established by ASHRAE 90.1-2007, Appendix G. Option 1 establishes a computer model of the building’s architectural design and all mechanical, electrical, domestic hot water, plug load, and other energy-consuming systems and devices. The model incorporates the occupancy load and a schedule representing projected usage in order to predict energy use. This compliance path does not prescribe any technology or strategy, but requires a minimum reduction in total energy cost of 10% (5% for an existing building), compared to a baseline building with the same form and design but using systems compliant with ASHRAE 90.1-2007. You can earn additional LEED points through EAc1 for cost reductions of 12% and greater (8% for existing buildings). 


  • Option 2: Prescriptive Compliance Path: ASHRAE Advanced Energy Design Guide refers to design guides published by ASHRAE for office, school, warehouse, and retail projects. These guides outline strategies to reduce energy use by 30% from ASHRAE 90.1-2001 levels, or an amount equivalent to a 10%–14% reduction from the ASHRAE 90.1-2007 standard. If you choose this compliance path, become familiar with the list of prescriptive requirements and commit to meeting them. (See the AEDG checklist in the Documentation Toolkit.) 


  • Option 3: Prescriptive Compliance Path: Advanced Buildings Core Performance Guide is another, more basic prescriptive path. It’s a good option if your project is smaller than 100,000 ft2, cannot pursue Option 2 (because there is not an ASHRAE guide for the building type), is not a healthcare facility, lab, or warehouse—or you would rather not commit to the energy modeling required for Option 1. Your project can be of any other building type (such as office or retail). To meet the prerequisite, you must comply with all requirements within Sections 1 and 2 of the guide. If you choose this path, become familiar with the list of activities and requirements and commit to meeting them. (See Resources for a link to the Core Performance Guide and the Documentation Toolkit for the checklist of prescriptive items.)


  • EAc1: Optimize Energy Performance uses the same structure of Options 1–3, so it makes sense to think about the credit and the prerequisite together when making your choice. In EAc1, Option 1 offers the potential for far more points than Options 2 and 3, so if you see your project as a likely candidate for earning those points, Option 1 may be best.


  • Hotels, multifamily residential, and unconventional commercial buildings may not be eligible for either Option 2 or Option 3, because the prescriptive guidance of these paths was not intended for them. Complex projects, unconventional building types, off-grid projects, or those with high energy-reduction goals are better off pursuing Option 1, which provides the opportunity to explore more flexible and innovative efficiency strategies and to trade off high-energy uses for lower ones. 


  • If your project combines new construction and existing building renovation then whatever portion contains more than 50% of the floor area would determine the energy thresholds.


  • Options 2 and 3 are suitable for small, conventional building types that may not have as much to gain from detailed energy modeling with Option 1. 


  • Meeting the prescriptive requirements of Options 2 and 3 is not common practice and requires a high degree of attention to detail by your project team. (See the Documentation Toolkit for the Core Performance Guide Checklist.) These paths are more straightforward than Option 1, but don’t think of them as easy. 


  • Options 2 and 3 require additional consultant time from architects and MEP engineers over typical design commitment, which means higher upfront costs. 


  • Option 1 references the mandatory requirements of ASHRAE 90.1-2007, which are more stringent than earlier LEED rating systems that referred to ASHRAE 90.1-2004.


  • Option 1 energy simulation provides monthly and annual operating energy use and cost breakdowns. You can complete multiple iterations, refining energy-efficiency strategies each time. Payback periods can be quickly computed for efficiency strategies using their additional first costs. A building’s life is assumed to be 60 years. A payback period of five years is considered a very good choice, and 10 years is typically considered reasonable. Consult the OPR for your owners’ goals while selecting your efficiency strategies. 


  • Option 1 energy simulation often requires hiring an energy modeling consultant, adding a cost (although this ranges, it is typically on the order of $0.10–$0.50/ft2 depending on the complexity). However, these fees produce high value in terms of design and decision-making assistance, and especially for complex or larger projects can be well worth the investment. 


  • All compliance path options may require both the architectural and engineering teams to take some time in addition to project management to review the prescriptive checklists, fill out the LEED Online credit form, and develop the compliance document. 


  • Option 1: Whole Building Energy Simulation


  • The architect, mechanical engineer, and lighting designer need to familiarize themselves and confirm compliance with the mandatory requirements of ASHRAE 90.1-2007, sections 5–9.


  • Use simple computer tools like SketchUp and Green Building Studio that are now available with energy analysis plug-ins to generate a first-order estimate of building energy use within a climate context and to identify a design direction. Note that you may need to refer to different software may not be the one used to develop complete the whole building energy simulations necessary for LEED certification. 


  • Energy modeling can inform your project team from the start of design. Early on, review site climate data—such as temperature, humidity and wind, available from most energy software—as a team. Evaluate the site context and the microclimate, noting the effects of neighboring buildings, bodies of water, and vegetation. Estimate the distribution of energy across major end uses (such as space heating and cooling, lighting, plug loads, hot water, and any additional energy uses), targeting high-energy-use areas to focus on during design.  


  • Energy use breakdown pie chartUse a preliminary energy use breakdown like this one to identify target areas for energy savings.Perform preliminary energy modeling in advance of the schematic design phase kick-off meeting or design charrette. The energy use breakdown can help identify targets for energy savings and point toward possible alternatives. 


  • For existing buildings, the baseline energy model can reflect the pre-renovation features like rather than a minimally ASHRAE-compliant building. This will help you achieve additional savings in comparison with the baseline.


  • Projects generating renewable energy onsite should use Option 1 to best demonstrate EAp2 compliance and maximize points under EAc1. Other options are possible but won’t provide as much benefit. Like any other project, model the baseline case as a system compliant with ASHRAE 90.1-2007, using grid-connected electricity, and the design case is an “as-designed” system also using grid-connected electricity. You then plug in 100% onsite renewable energy in the final energy-cost comparison table, as required by the performance rating method (PRM) or the modeling protocol of ASHRRAE 90.1 2007, Appendix G. (Refer to the sample PRM tables in the Documentation Toolkit for taking account of onsite renewable energy.


  • LEED divides energy-using systems into two categories: 

    • (i) Regulated loads. Most prominent systems—space heating, cooling, ventilation and pumps, lighting, and hot water—are regulated by ASHRAE and LEED so are termed “regulated” loads. Your energy model can provide insights into the energy use of all these systems. 
    • (ii) Non-regulated loads are those which are not directly associated with creating a comfortable environment, but with plug loads for machines. These include elevators, kitchen equipment, office equipment, televisions, and activity-oriented lighting, such as in hospitals. Though these are very large energy loads, they are not regulated by ASHRAE 90.1 or by LEED. Energy savings from specifying better equipment is not counted in energy models. It is typically expected that these non-regulated loads contribute to 25% of energy use.

  • The energy model itself will not account for any change in plug loads from the baseline case, even if your project is making a conscious effort to purchase Energy Star or other efficient equipment. Any improvement made in plug loads must be documented separately, using the exceptional calculation methodology (ECM), as described in ASHRAE 90.1-2007. These calculations determine the design case energy cost compared to the baseline case. They are included in the performance rating method (PRM) table or directly in the baseline and design case model. 


  • Besides energy modeling, you may need to use the exceptional calculation methodology (ECM) when any of the following situations occur: 

    • The energy software cannot carry out calculations for a specific systems like natural ventilation or unusual HVAC equipment.
    • Process loads are different in baseline and design cases and can influence total energy cost savings.
    • The proposed design can’t demonstrate savings with the modeling protocol and needs additional calculations. 

  • Some energy-modeling software tools have a daylight-modeling capability. Using the same model for both energy and IEQc8.1: Daylight and Views—Daylight can greatly reduce the cost of your modeling efforts.


  • Option 2: Prescriptive Compliance Path—ASHRAE Advanced Energy Design Guides


  • Provide a copy of the AEDG for office, retail, or warehouse, as applicable, to each team member as everyone, including the architect, mechanical and electrical engineers, lighting designer, and commissioning agents, are responsible for ensuring compliance. These are available to download free from the ASHRAE website. (See Resources.) 


  • Find your climate zone before attempting to meet any detailed prescriptive requirements. Climate zones vary by county, so be sure to select the right one. (See the Documentation Toolkit for a list of climate zones by county.)


  • Develop a checklist of all requirements, and assign responsible team members to accomplish them. Hold a meeting to walk the team through the AEDG checklist for your project’s climate zone. Clarify specific design goals and prescriptive requirements in the OPR for EAp1: Fundamental Commissioning.


  • Early access to the AEDG by each team member avoids last-minute changes that can have cascading, and costly, effects across many building systems. 


  • The AEDG prescriptive requirements include: 

    • a maximum allowable window-to-wall ratio;
    • continuous insulation on the outside of walls;
    • roofs and floor-slab minimum thermal performance;
    • minimum window and door thermal performance;
    • minimum boiler and chiller efficiencies;
    • and mandatory use economizers or heat recovery ventilation.

    If your project team is not comfortable following these guidelines, consider switching to Option 1, which gives you more flexibility. 


  • Although Option 2 is generally lower cost during the design phase than energy modeling, the compliance path is top heavy—it requires additional meeting time upfront for key design members. 


  • Option 3: Prescriptive—Advanced Buildings Core Performance Guide


  • Provide a copy of the New Buildings Institute Advanced Buildings: Core Performance Guide to each team member. The guide is available to download free from the NBI website. (See Resources.) 


  • The guide provides practical design assistance that can be used throughout the design process.


  • Walk your team through the project checklist to clarify design goals and prescriptive requirements. 


  • The guide provides an outline for approaching an energy-efficient design, in addition to a list of prescriptive measures. The first of its three sections emphasizes process and team interaction rather than specific building systems or features. Advise the owner to read through the guide in order to understand what is required of the architect and engineers. 


  • Section 1 in the guide focuses on best practices that benefit the project during the pre-design and schematic design stages, such as analyzing alternative designs and writing the owner’s project requirements (OPR). 


  • Section 2 of the Core Performance Guide describes architectural, lighting, and mechanical systems to be included. Section 3 is not required for EAp2 but includes additional opportunities for energy savings that can earn EAc1 points. 


  • The guide mandates that your team develop a minimum of three different design concepts to select from for best energy use.


  • Though they can be a little daunting at first glance, a majority of the guide’s requirements overlap with other LEED credits, such as EAp1: Fundamental Commissioning, IEQp1: Minimum Indoor Air Quality Performance, and IEQc6.1: Controllability of Systems—Lighting Controls


  • This compliance path is top-heavy due to upfront consultant time, but it provides adequate structure to ensure that your project is in compliance with the prerequisite requirements. For some projects it may be less expensive to pursue than Option 1. 

Schematic Design

Expand All

  • The owner should now have finalized the OPR with the support of the architect, as part of the commissioning credits EAp1 and EAc3. The goals identified here will help your team identify energy-reduction and occupant-comfort strategies.


  • Consider a broad range of energy-efficiency strategies and tools, including passive solar, daylighting, cooling-load reduction, and natural ventilation to reduce heating and cooling loads. 


  • Develop the basis of design (BOD) document in conjunction with your mechanical engineer and architect for EAp1: Fundamental Commissioning, noting key design parameters to help strategize design direction as outlined in the OPR. 


  • The OPR and BOD serve the larger purpose of documenting the owner’s vision and your team’s ideas to meet those goals. The BOD is intended to be a work-in-progress and should be updated at all key milestones in your project. Writing the document gives you an opportunity to capture the owner’s goals, whether just to meet the prerequisite or to achieve points under EAc1.


  • Confirm that your chosen compliance path is the most appropriate for your project, and make any changes now. Following a review with the design team and owner, ensure that everyone is on board with contracting an energy modeler for Option 1 or meeting all the prescriptive requirements under Options 2 or 3. 


  • Sometimes teams change from Option 1 to Options 2 or 3 very late in the design phase for various reasons including not realizing the cost of energy modeling. Making that change is risky, though: the prescriptive paths are all-or-nothing—you must comply with every item, without exception. Evaluate each requirement and consult with the contractor and estimator to ensure the inclusion of all activities within project management. 


  • To avoid costly, last-minute decisions, develop a comprehensive, component-based cost model as a decision matrix for your project. The model will help establish additional cost requirements for each energy conservation measure. It will also illustrate cost reductions from decreased equipment size, construction rendered unnecessary by energy conservation measures, and reduced architectural provisions for space and equipment access. (See the Documentation Toolkit for an example.)


  • Use envelope design and passive strategies to reduce the heating and cooling loads prior to detailed design of HVAC systems. Passive strategies can reduce heating and cooling loads, giving the engineer more options, including smaller or innovative systems.


  • Load reduction requires coordinated efforts by all design members including the architect, lighting designer, interior designer, information-technology manager, and owner. 

    • Architects can choose the optimum building orientation, select the appropriate envelope system and design it to be tight, and configure programming to utilize passive strategies as much as possible. 
    • Lighting designers help by harvesting daylight, making appropriate fixture selections, minimizing lighting layouts (fewer fixtures), providing maximum controls and daylight and occupancy sensors to reduce wasted light. 
    • Interior designers are critical for selecting reflective finishes to enhance daylighting and specifying Energy Star appliances. 
    • IT specialists are important, especially in buildings with data centers, for selection of computers and data-processing equipment that reduce the power load as well as cooling. 

  • Involving facilities staff in the design process can further inform key design decisions, helping ensure successful operation and low maintenance costs.


  • Encourage your design team to brainstorm design innovations and energy-reduction strategies. This provides a communication link among team members so they can make informed decisions. 


  • More energy-efficient HVAC equipment can cost more relative to conventional equipment. However, by reducing heating and cooling loads through good passive design, the mechanical engineer can often reduce the size and cost of the system. Reduced system size can save money through:

    • smaller chillers or boilers;
    • smaller fans, used less frequently;
    • smaller pumps and auxiliary systems;
    • smaller ducts;
    • and less square footage devoted to mechanical systems.

  • Review case studies of similar energy-efficient buildings in the same climate to provide helpful hints for selecting energy-efficiency measures. For example, a building in a heating-dominated climate can often benefit from natural ventilation and free cooling during shoulder seasons. (See Resources for leading industry journals showcasing success stories around the country and internationally.)


  • The relationship between first costs and operating costs can be complex. For example, more efficient windows will be more expensive, but could reduce the size and cost of mechanical equipment. A more efficient HVAC system may be more expensive, but will reduce operating costs. Play around with variables and different strategies to get the right fit for the building and the owner’s goals as stated in the OPR.


  • Option 1: Whole Building Energy Simulation


  • Review and confirm compliance with the mandatory requirements of all the relevant sections of ASHRAE 90.1-2007


  • Trust your project’s energy modeling task to a mechanical firm with a proven track record in using models as design tools, and experience with your building type.


  • Contract an energy modeling team for the project. These services may be provided by the mechanical engineering firm on the design team or by an outside consultant. Software used for detailed energy use analysis and submitted for final LEED certification must be accepted by the regulatory authority with jurisdiction, and must comply with paragraph G2.2 of ASHRAE Standard 90.1-2007. Refer to Resources for a list of Department of Energy approved energy-analysis software that may be used for LEED projects.


  • Design team members, including the architect and mechanical engineer at a minimum, need to work together to identify a percentage improvement goal for project energy use over the ASHRAE 90.1-2007-compliant baseline model. The percentage should be at least 10% to meet the prerequisite. 


  • Plan on initiating energy modeling during the design process, and use it to inform your design—preferably executing several iterations of the design as you improve the modeled energy performance. 


  • Ask the modeling consultant to develop an annual energy-use breakdown—in order to pick the “fattest” targets for energy reduction. A typical energy-use breakdown required for LEED submission and ASHRAE protocol includes: 

    • lighting;
    • space heating;
    • space cooling;
    • domestic hot water;
    • additional installed heat recovery, refrigeration, or heat-rejection systems;
    • ventilation fans and auxiliary pumps;
    • and equipment and plug loads. 

  • Identify critical areas in which to reduce loads. For example, in a data center, the plug loads are the largest energy load. Small changes in lighting density might bring down the energy use but represent only a small fraction of annual energy use. 


  • Don't forget that LEED (following ASHRAE) uses energy cost and not straight energy when it compares your design to a base case. That's important because you might choose to use a system that burns natural gas instead of electricity and come out with a lower cost, even though the on-site energy usage in kBtus or kWhs is higher. Generally you have to specify the same fuel in your design case and in the base case, however, so you can't simply switch fuels to show a cost savings


  • Explore and analyze design alternatives for energy use analyses to compare the cost-effectiveness of your design choices. For example, do you get better overall performance from a better window or from adding a PV panel? Will demand-control ventilation outperform increased ceiling insulation?


  • Simple, comparative energy analyses of conceptual design forms are useful ways to utilize an energy model at this stage. Sample scenarios include varying the area of east-facing windows and looking at 35% versus 55% glazing. Each scenario can be ranked by absolute energy use to make informed decisions during the design stage. 


  • If your project is using BIM software, the model can be plugged into the energy analysis software to provide quick, real-time results and support better decisions. 


  • Model development should be carried out following the PRM from ASHRAE 90.1-2007, Appendix G, and the LEED 2009 Design and Construction Reference Guide, Table in EAc1. In case of a conflict between ASHRAE and LEED guidelines, follow LEED.


  • Projects using district energy systems have special requirements. For EAp2, the proposed building must achieve the 10% energy savings without counting the effects of the district generation system. To earn points in EAc1 you can take advantage of the district system’s efficiency, but you have to run the energy model again to claim those benefits (see EAc1 for details). 


  • While you could run the required energy model at the end of the design development phase, simply to demonstrate your prerequisite compliance, you don’t get the most value that way in terms of effort and expense. Instead, do it early in the design phase, and run several versions as you optimize your design. Running the model also gives you an opportunity to make improvements if your project finds itself below the required 10% savings threshold.


  • The baseline model is the designed building with mechanical systems specified in ASHRAE 90.1-2007, Appendix G, for the specific building type, with a window-to-wall ratio at a maximum of 40%, and minimally code-compliant specifications for the envelope, lighting, and mechanical components. It can be developed as soon as preliminary drawings are completed. The baseline is compared to the design case to provide a percentage of reduction in annual energy use. To avoid any bias from orientation, you need to run the baseline model in each of the four primary directions, and the average serves as your final baseline figure. 


  • The design-case is modeled using the schematic design, orientation, and proposed window-to-wall ratio—¬the model will return design-case annual energy costs. Earn points by demonstrating percentage reductions in annual energy costs from the design to the baseline case. EAp2 is achieved if the design case is 10% lower than the baseline in new construction (or 5% less in existing building renovations). 


  • Provide as much project and design detail to the modeler as possible. A checklist is typically developed by the energy modeler, listing all the construction details of the walls, roof, slabs, windows, mechanical systems, equipment efficiencies, occupancy load, and schedule of operations. Any additional relevant information or design changes should be brought to the modeler’s attention as soon as possible. The more realistic the energy model is, the more accurate the energy use figure, leading to better help with your design.


  • Invite energy modelers to project meetings. An experienced modeler can often assist in decision-making during design meetings, even without running complete models each time. 


  • All known plug loads must be included in the model. The baseline and design-case models assume identical plug loads. If your project is deliberately attempting to reduce plug loads, demonstrate this by following the exceptional calculation method (ECM), as described in ASHRAE 90.1-2007, G2.5. Incorporate these results in the model to determine energy savings. 


  • For items outside the owner’s control—like lighting layout, fans and pumps—the parameters for the design and baseline models must be identical.


  • It can take anywhere from a few days to a few weeks to generate meaningful energy modeling results. Schedule the due dates for modeling results so that they can inform your design process.


  • Review the rate structure from your electrical utility. The format can inform your team of the measures likely to be most effective in reducing energy costs, especially as they vary over season, peak load, and additional charges beyond minimum energy use.


  • Performing a cost-benefit analysis in conjunction with energy modeling can determine payback times for all the energy strategies, helping the iterative design process.


  • Using energy modeling only to check compliance after the design stage wastes much of the value of the service, and thus your investment.


  • Option 2: Prescriptive—ASHRAE Advanced Energy Design Guides 


  • The architect and mechanical engineer should carefully read the applicable ASHRAE Advanced Energy Design Guide for office, warehouse, or retail projects, as applicable. 


  • Keep the owner abreast of the design decisions dictated by the standard. Fill in the team-developed checklist, within the climate zone table’s prescribed requirements, with appropriate envelope improvements, system efficiencies, and a configuration that meets the standard requirements. 


  • As a prescriptive path, this option relies heavily on following the requirement checklist, which is used throughout the design process to track progress. To assist design development, provide all critical team members—not limited to the architect, mechanical and electrical engineers, and lighting designer—with a checklist highlighting their appointed tasks.


  • The architect, mechanical engineer, and lighting designer need to discuss each requirement and its design ramifications. Hold these meetings every six to eight weeks to discuss progress and make sure all requirements are being met.


  • Confirm that your project team is comfortable with following all the prescribed requirements. If not, switch to Option 1: Whole Building Energy Simulation. 


  • The LEED Online credit form does not specify how to document each prescriptive requirement because they are so different for each project; it only requires a signed confirmation by the MEP for meeting AEDG requirements. You still have to provide documentation. Submit your checklist of requirements, and supporting information for each item, through LEED Online to make your case. If your project fails to meet even one requirement, it will fail to earn the prerequisite, thus jeopardizing LEED certification.  


  • Although energy modeling consultant costs are avoided by this option, additional staff time will be required to document and track compliance status, as compared with conventional projects.


  • Energy efficiency measures prescribed by the guide can be perceived as additional costs in comparison with conventional projects. However, they are easy to implement and are cost-effective pn the whole.


  • Option 3: Prescriptive Compliance Path—Advanced Buildings Core Performance Guide 


  • Become familiar with the Core Performance Guide early in the design phase to know the multiple requirements and all requisite documents.


  • Note that the guide demands additional time, attention, and integrated process from the design team as compared to conventional projects. It’s not just a list of prescriptive requirements, but a prescribed process for achieving energy efficiency goals. LEED Online documentation requires proof of all steps outlined in Sections 1 and 2, including three conceptual design options and meeting minutes. The project manager, architect, and mechanical engineer should read the complete Core Performance Guide carefully to know beforehand the prescriptive requirements in Sections 1 and 2. 


  • The project manager must take responsibility for ensuring that the requirement checklist is on track.


  • For Section 3, the design team needs to identify three or more of the listed strategies as possible targets for the project. 


  • Create a checklist of requirements and assign a responsible party to each item. 


  • The Core Performance Guide requires an integrated design contributed by the architect, mechanical and electrical engineers, and lighting designer. The project manager must take responsibility for shepherding and documenting the collaborative process to demonstrate compliance. 


  • A long documentation list can be overwhelming for your team, so create a detailed checklist with tasks delegated to individual team members, allowing each member to focus on assigned tasks. The checklist can function as a status tracking document and, finally, the deliverable for LEED Online.

Design Development

Expand All

  • The architect and engineer, and other project team members, continue to develop a high-performance building envelope with efficient mechanical and lighting systems. 


  • Constant communication and feedback among project team members, owner, and if possible, operational staff, during design development can minimize construction as well as operational costs and keep your project on schedule. 


  • If you change or go through value-engineering on any specifications, such as the solar-heat gain coefficient of glazing, for example, be aware of impacts on mechanical system sizing. Making changes like this might not pay off as much as it first appears.


  • Consider using building information modeling (BIM) tools to keep design decisions up to date and well documented for all team members.


  • Schedule delays can be avoided if all team members share their ideas and update documents during the design development process. 


  • Option 1: Whole Building Energy Simulation


  • The modeler completes the energy analysis of the selected design and system and offers alternative scenarios for discussion. The modeler presents the energy cost reduction results to the team, identifying the LEED threshold achieved.


  • It’s helpful for the energy modeling report to include a simple payback analysis to assist the owner in making an informed decision on the operational savings of recommended features. 


  • The architect and HVAC engineer should agree on the design, working with the cost estimator and owner.


  • Demonstrating reductions in non-regulated loads requires a rigorous definition of the baseline case. The loads must be totally equivalent, in terms of functionality, to the proposed design case. For example, reducing the number of computers in the building does not qualify as a legitimate reduction in non-regulated loads. However, the substitution of laptops for desktop computers, and utilization of flat-screen displays instead of CRTs for the same number of computers, may qualify as a reduction.


  • Residential and hospitality projects that use low-flow showers, lavatories, and kitchen sinks (contributing to WEp1) benefit from lower energy use due to reduced overall demand for hot water. However, for energy-savings calculations, these are considered process loads that must be modeled as identical in baseline and design cases, or you have the choice of demonstrating the savings with ECM for process loads. 


  • Perform daylight calculations in conjunction with energy modeling to balance the potentially competing goals of more daylight versus higher solar-heat gain resulting in high cooling loads. 


  • If your project is pursuing renewable energy, the energy generated is accounted for by using the PRM. These results provide information about whether the energy is contributing to EAc2: Onsite Renewable Energy. 


  • A cost-benefit analysis can help the owner understand the return on investment of big-ticket, energy-conserving equipment that lowers operating energy bills with a quick payback. 


  • Complete at least half of the energy modeling effort by the end of the design development stage. Help the design team to finalize strategy through intensive, early efforts in energy modeling. Once the team has a design direction, the modeler can develop a second model during the construction documents phase for final confirmation. 


  • If pursuing ECM for non-regulated loads, calculate energy saving for each measure separately if you are, for example, installing an energy-efficient elevator instead of a typical one so that the reduction would contribute to total building energy savings. Calculate the anticipated energy use of the typical elevator in kBTUs or kWh. Using the same occupancy load, calculate the energy use of the efficient elevator. Incorporate the savings into design case energy use within the PRM. Refer to the ECM strategy for detailed calculation guidelines. 


  • Option 2: Prescriptive Compliance Path—ASHRAE Advanced Energy Design Guides 


  • Ensure that all prescriptive requirements are incorporated into the design by the end of the design development stage.


  • Revisit the Advanced Energy Design Guides (AEDG) checklist to ensure that the design meets the prescriptive requirements.


  • Option 3: Prescriptive Compliance Path—Advanced Buildings Core Performance Guide


  • The mechanical engineer, lighting consultant, and architect revisit the checklist for an update on the requirements and how they are being integrated into the design. All prescriptive requirements should be specifically incorporated into the design by the end of the design development phase. 


  • The mechanical engineer and architect track the status of each requirement.


  • While the LEED Online credit form does not require detailed documentation for each Core Performance Guide requirement, it is important that each item be documented as required and reviewed by the rest of the team to confirm compliance, especially as further documentation may be requested by during review. Your design team should work with the owner to identify cost-effective strategies from Section 3 that can be pursued for the project. 

Construction Documents

Expand All

  • Construction documents clearly detail the architectural and mechanical systems that address energy-efficiency strategies.  


  • Confirm that specifications and the bid package integrate all equipment and activities associated with the project. 


  • If the project goes through value engineering, refer to the OPR and BOD to ensure that no key comfort, health, productivity, daylight, or life-cycle cost concerns are sacrificed.


  • During the budget estimating phase, the project team may decide to remove some energy-saving strategies that have been identified as high-cost items during the value-engineering process. However, it is very important to help the project team understand that these so-called add-ons are actually integral to the building’s market value and the owner’s goals. 


  • Removing an atrium, for example, due to high cost may provide additional saleable floor area, but may also reduce daylight penetration while increasing the lighting and conditioning loads.  


  • Option 1: Whole Building Energy Simulation


  • Although this prerequisite is a design-phase submittal, it may make sense to submit it, along with EAc1, after construction. Your project could undergo changes during construction that might compel a new run of the energy model to obtain the latest energy-saving information. Waiting until the completion of construction ensures that the actual designed project is reflected in your energy model.


  • Create a final energy model based completely on construction document drawings—to confirm actual energy savings as compared to ASHRAE 90.1-2007 requirements. An energy model based on the construction documents phase will provide realistic energy-cost savings and corresponding LEED points likely to be earned. 


  • Make sure the results fit the LEED Online credit form requirements. For example, the unmet load hours have to be less than 300 and process loads will raise a red flag if they’re not approximately 25%. If any of the results are off mark, take time to redo the model. Time spent in design saves more later on in the LEED review process. 


  • Option 2: Prescriptive Compliance Path—ASHRAE Advanced Energy Design Guides


  • Finalize all design decisions and confirm that you’ve met all of the prescriptive requirements. Your team must document the checklist with relevant project drawings, including wall sections, specifications, and the MEP drawing layout.


  • Value engineering and other factors can result in design changes that eliminate certain energy features relevant to the prerequisite. As this compliance path is prescriptive, your project cannot afford to drop even one prescribed item.


  • Option 3: Prescriptive Compliance Path—Advanced Buildings Core Performance Guide


  • Finalize all design decisions and confirm that you’ve met all of the prescriptive requirements. Your team must document the checklist with relevant project drawings, including wall sections, specifications, and the MEP drawing layout.


  • Value engineering and other factors can result in design changes that eliminate certain energy features relevant to the credit. As this compliance path is prescriptive, your project cannot afford to drop even one listed item. Although perceived as high-cost, prescriptive requirements lower energy costs during operation and provide a simple payback structure. 

Construction

Expand All

  • The architect and mechanical engineer review the shop drawings to confirm the installation of the selected systems. 


  • The commissioning agent and the contractor conduct functional testing of all mechanical equipment in accordance with EAp1: Fundamental Commissioning and EAc3: Enhanced Commissioning. 


  • Find your Energy Star rating with EPA’s Target Finder tool if your building type is in the database. Input your project location, size, and number of occupants, computers, and kitchen appliances. The target may be a percentage energy-use reduction compared to a code-compliant building, or “anticipated energy use” data from energy model results. Add information about your fuel use and rate, then click to “View Results.” Your Target Finder score should be documented at LEED Online.


  • Plan for frequent site visits by the mechanical designer and architect during construction and installation to make sure construction meets the design intent and specifications. 


  • Emphasize team interaction and construction involvement when defining the project scope with key design team members. Contractor and designer meetings can help ensure correct construction practices and avoid high change-order costs for the owner. 


  • Subcontractors may attempt to add a premium during the bidding process for any unusual or unknown materials or practices, so inform your construction bidders of any atypical design systems at the pre-bid meeting.


  • Option 1: Whole Building Energy Simulation


  • The energy modeler ensures that any final design changes have been incorporated into the updated model.


  • Upon finalizing of the design, the responsible party or energy modeler completes the LEED Online submittal with building design inputs and a PRM result energy summary. 


  • Although EAp2 is a design phase submittals, it may make sense to submit it (along with EAc1) after construction. Your project could undergo changes during construction that might require a new run of the energy model. Waiting until the completion of construction ensures that your actual designed project is reflected. On the other hand, it gives you less opportunity to respond to questions that might come up during a LEED review. 


  • Include supporting documents like equipment cut sheets, specifications and equipment schedules to demonstrate all energy efficiency measures claimed in the building. 


  • It common for the LEED reviewers to make requests for more information. Go along with the process—it doesn’t mean that you’ve lost the credit. Provide as much information for LEED Online submittal as requested and possible. 


  • Option 2: Prescriptive Compliance Path—ASHRAE Advanced Energy Design Guides (AEDG)


  • The design team completes the LEED Online documentation, signing off on compliance with the applicable AEDG, and writing the narrative report on the design approach and key highlights.


  • During LEED submission, the project team needs to make an extra effort to support the prerequisite with the completed checklist and the required documents. Although the LEED rating system does not list detailed documentation, it is best practice to send in supporting documents for the prescriptive requirements from the AEDG. The supporting documents should include relevant narratives, wall sections, mechanical drawings, and calculations. 


  • Although the LEED Online sign-off does not include a checklist of AEDG requirements, it assumes that the team member is confirming compliance with all detailed requirements of the guide. 


  • Option 3: Prescriptive Compliance Path—Advanced Building Core Performance Guide


  • The design team completes the LEED Online credit form, signing off on compliance with the Core Performance Guide, and writing the narrative report on the design approach and key highlights.


  • During LEED submission, your project team needs to make an extra effort to support the prerequisite with the completed checklist and the required documents. Although not every requirement may be mentioned in the LEED documentation, the supporting documents need to cover all requirements with narratives, wall sections, mechanical drawings, and calculations. 


  • Many of this option’s compliance documents are common to other LEED credits or design documents, thus reducing duplicated efforts. 

Operations & Maintenance

Expand All

  • Develop an operations manual with input from the design team in collaboration with facility management and commissioning agent if pursuing EAc3: Enhanced Commissioning. 


  • The benefit of designing for energy efficiency is realized only during operations and maintenance. Record energy use to confirm that your project is saving energy as anticipated. If you are not pursuing EAc5: Measurement and Verification, you can implement tracking procedures such as reviewing monthly energy bills or on-the-spot metering.


  • Some energy efficiency features may require special training for operations and maintenance personnel. For example, cogeneration and building automation systems require commissioning and operator training. Consider employing a trained professional to aid in creating operation manuals for specialty items. 


  • Energy-efficiency measures with a higher first cost often provide large savings in energy use and operational energy bills. These credit requirements are directly tied to the benefits of efficient, low-cost operations.

  • USGBC

    Excerpted from LEED 2009 for New Construction and Major Renovations

    EA Prerequisite 2: Minimum energy performance

    Required

    Intent

    To establish the minimum level of energy efficiency for the proposed building and systems to reduce environmental and economic impacts associated with excessive energy use.

    Requirements

    Projects that registered on or after April 8, 2016 must demonstrate an 18% improvement for new buildings, or a 14% improvement for major renovations to existing buildings.
    Option 1. Whole building energy simulation

    Demonstrate a 10% improvement in the proposed building performance rating for new buildings, or a 5% improvement in the proposed building performance rating for major renovations to existing buildings, compared with the baseline building performanceBaseline building performance is the annual energy cost for a building design, used as a baseline for comparison with above-standard design. rating.

    Calculate the baseline building performance rating according to the building performance rating method in Appendix G of ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1) using a computer simulation model for the whole building project. Projects outside the U.S. may use a USGBC approved equivalent standard2.

    Appendix G of Standard 90.1-2007 requires that the energy analysis done for the building performance rating method include all energy costs associated with the building project. To achieve points using this credit, the proposed design must meet the following criteria:

    • Comply with the mandatory provisions (Sections 5.4, 6.4, 7.4, 8.4, 9.4 and 10.4) in Standard 90.1-2007 (with errata but without addenda1) or USGBC approved equivalent.
    • Inclusion of all the energy costs within and associated with the building project.
    • Compare against a baseline building that complies with Appendix G of Standard 90.1-2007 (with errata but without addenda1) or USGBC approved equivalent. The default process energy cost is 25% of the total energy cost for the baseline building. If the building’s process energy cost is less than 25% of the baseline building energy cost, the LEED submittal must include documentation substantiating that process energy inputs are appropriate.

    For the purpose of this analysis, process energy is considered to include, but is not limited to, office and general miscellaneous equipment, computers, elevators and escalators,kitchen cooking and refrigeration, laundry washing and drying, lighting exempt from the lighting power allowance (e.g., lighting integral to medical equipment) and other (e.g., waterfall pumps).

    Regulated (non-process) energy includes lighting (for the interior, parking garage, surface parking, façade, or building grounds, etc. except as noted above), heating, ventilation and air conditioning (HVAC) (for space heating, space cooling, fans, pumps, toilet exhaust, parking garage ventilation, kitchen hood exhaust, etc.), and service water heating for domestic or space heating purposes.

    Process loads must be identical for both the baseline building performance rating and the proposed building performance rating. However, project teams may follow the exceptional calculation method (ANSI/ASHRAE/IESNA Standard 90.1-2007 G2.5) or USGBC approved equivalent to document measures that reduce process loads. Documentation of process load energy savings must include a list of the assumptions made for both the base and the proposed design, and theoretical or empirical information supporting these assumptions.

    Projects in California may use Title 24-2005, Part 6 in place of ANSI/ASHRAE/IESNA Standard 90.1-2007 for Option 1.

    OR

    Option 2 is not an eligible compliance option for projects that registered on or after April 8, 2016.
    Option 2. Prescriptive compliance path: ASHRAE Advanced Energy Design Guide

    Comply with the prescriptive measures of the ASHRAE Advanced Energy Design Guide appropriate to the project scope, outlined below. Project teams must comply with all applicable criteria as established in the Advanced Energy Design Guide for the climate zoneOne of five climatically distinct areas, defined by long-term weather conditions which affect the heating and cooling loads in buildings. The zones were determined according to the 45-year average (1931-1975) of the annual heating and cooling degree-days (base 65 degrees Fahrenheit). An individual building was assigned to a climate zone according to the 45-year average annual degree-days for its National Oceanic and Atmospheric Administration (NOAA) Division. in which the building is located. Projects outside the U.S. may use ASHRAE/ASHRAE/IESNA Standard 90.1-2007 Appendices B and D to determine the appropriate climate zone.

    Path 1. ASHRAE Advanced Energy Design Guide for Small Office Buildings 2004

    The building must meet the following requirements:

    • Less than 20,000 square feet (1,800 square meters).
    • Office occupancy.
    Path 2. ASHRAE Advanced Energy Design Guide for Small Retail Buildings 2006

    The building must meet the following requirements:

    • Less than 20,000 square feet (1,800 square meters).
    • Retail occupancy.
    Path 3. ASHRAE Advanced Energy Design Guide for Small Warehouses and Self Storage Buildings 2008

    The building must meet the following requirements:

    • Less than 50,000 square feet (4,600 square meters).
    • Warehouse or self-storage occupancy.

    OR

    Option 3 is not an eligible compliance option for projects that registered on or after April 8, 2016.
    Option 3. Prescriptive compliance path: Advanced Buildings™ Core Performance™ Guide

    Comply with the prescriptive measures identified in the Advanced Buildings™ Core Performance™ Guide developed by the New Buildings Institute. The building must meet the following requirements:

    • Less than 100,000 square feet (9,300 square meters).
    • Comply with Section 1: Design Process Strategies, and Section 2: Core Performance Requirements.
    • Health care, warehouse and laboratory projects are ineligible for this path.

    Projects outside the U.S. may use ASHRAE/ASHRAE/IESNA Standard 90.1-2007 Appendices B and D to determine the appropriate climate zone.

    OR

    Option 4. Brazil compliance path: PBE Edifica

    Projects in Brazil that are certified at the “A” level under the Regulation for Energy Efficiency Labeling (PBE Edifica) program for all attributes (Envelope, Lighting, HVAC) achieve this prerequisite. The following building types cannot achieve this prerequisite using this option: Healthcare, Data Centers, Manufacturing Facilities, Warehouses, and Laboratories.

    1Project teams wishing to use ASHRAE approved addenda for the purposes of this prerequisite may do so at their discretion. Addenda must be applied consistently across all LEED credits.

    2 Projects outside the U.S. may use an alternative standard to ANSI/ASHRAE/IESNA Standard 90.1-2007 if it is approved by USGBC as an equivalent standard using the process identified in the LEED 2009 Green Building Design and Construction Global ACP Reference Guide Supplement.

    Pilot ACPs Available

    The following pilot alternative compliance path is available for this prerequisite. See the pilot credit library for more information.

    EApc95: Alternative Energy Performance Metric ACP

    Potential Technologies & Strategies

    Design the building envelope and systems to meet baseline requirements. Use a computer simulation model to assess the energy performance and identify the most cost-effective energy efficiency measures. Quantify energy performance compared with a baseline building.

    If local code has demonstrated quantitative and textual equivalence following, at a minimum, the U.S. Department of Energy (DOE) standard process for commercial energy code determination, then the results of that analysis may be used to correlate local code performance with ANSI/ASHRAE/IESNA Standard 90.1-2007. Details on the DOE process for commercial energy code determination can be found at http://www.energycodes.gov/implement/
    determinations_com.stm.

    FOOTNOTES

    1 Project teams wishing to use ASHRAE approved addenda for the purposes of this prerequisite may do so at their discretion. Addenda must be applied consistently across all LEED credits.

    2 Projects outside the U.S. may use an alternative standard to ANSI/ASHRAE/IESNA Standard 90.1‐2007 if it is approved by USGBC as an equivalent standard using the process located at www.usgbc.org/leedisglobal

Organizations

Database of State Incentives for Renewables and Efficiency (DSIRE)

This database shows state-by-state incentives for energy efficiency, renewable energy, and other green building measures. Included in this database are incentives on demand control ventilation, ERVs, and HRVs.


New York State Energy Research and Development Authority (NYSERDA)

Useful web resource with information on local/regional incentives for energy-efficiency programs.


American Council for an Energy-Efficient Economy

ACEEE is a nonprofit organization dedicated to advancing energy efficiency through technical and policy assessments; advising policymakers and program managers; collaborating with businesses, public interest groups, and other organizations; and providing education and outreach through conferences, workshops, and publications. 


New Buildings Institute

The New Buildings Institute is a nonprofit, public-benefits corporation dedicated to making buildings better for people and the environment. Its mission is to promote energy efficiency in buildings through technology research, guidelines, and codes.


U.S. Department of Energy, Building Energy Codes Program

The Building Energy Codes program provides comprehensive resources for states and code users, including news, compliance software, code comparisons, and the Status of State Energy Codes database. The database includes state energy contacts, code status, code history, DOE grants awarded, and construction data. The program is also updating the COMcheck-EZ compliance tool to include ANSI/ASHRAE/IESNA 90.1–2007. This compliance tool includes the prescriptive path and trade-off compliance methods. The software generates appropriate compliance forms as well. 


Rensselaer Polytechnic Institute: Daylighting Resources

Research center at RPI provides access to a wide range of  daylighting resources, case studies, design tools, reports, publications and more.


IBPSA

International association of energy modelers with various national and local chapters. 


Architecture 2030

Non-profit organization aiming at design community to increase collaboration for designing energy efficient buildings.


Low Impact Hydropower Institute

The Low Impact Hydropower Institute is a non-profit organization and certification body that establishes criteria against which to judge the environmental impacts of hydropower projects in the United States.


U.S. Department of Energy Building Technologies Program

The Building Technologies Program (BTP) provides resources for commercial and residential building components, energy modeling tools, building energy codes, and appliance standards including the Buildings Energy Data Book, High Performance Buildings Database and Software Tools Directory.

Web Tools

Energy Analysis Tools

This website discusses the step-by-step process for energy modeling.


Advanced Buildings Technologies and Practices

This online resource, supported by Natural Resources Canada, presents energy-efficient technologies, strategies for commercial buildings, and pertinent case studies.


U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy

This website is a comprehensive resource for U.S. Department of Energy information on energy efficiency and renewable energy and provides access to energy links and downloadable documents. 


U.S. EPA, Combined Heat and Power Partnership

Information on cogenerationThe simultaneous production of electric and thermal energy in on-site, distributed energy systems; typically, waste heat from the electricity generation process is recovered and used to heat, cool, or dehumidify building space. Neither generation of electricity without use of the byproduct heat, nor waste-heat recovery from processes other than electricity generation is included in the definition of cogeneration., also called combined heat and power, is available from EPA through the CHPCombined heat and power (CHP), or cogeneration, generates both electrical power and thermal energy from a single fuel source. Partnership. The CHP Partnership is a voluntary program seeking to reduce the environmental impact of power generation by promoting the use of CHP. The Partnership works closely with energy users, the CHP industry, state and local governments, and other clean energy stakeholders to facilitate the development of new projects and to promote their environmental and economic benefits. 


Advanced Energy Design Guides

Free download of AHSRAE energy savings guide, use for Option 2.


Lawrence Berkeley Lab: Building Technologies Department

Research warehouse for strategies and case studies of energy efficiency in buildings.


Efficient Windows Collaborative

An online window selection tool with performance characteristics.


Whole Building Design Guide (WBDG)

This website lays out design process for developing an energy efficient building.


AIA Sustainability 2030 Toolkit

This website discusses ways to improve design for lower energy demand as they relate to the AIA 2030 challenge.


Windows for High-Performance Commercial Buildings

This website includes discussion of design issues, materials and assemblies, window design decisions and case studies. 


California Integrated Waste Management Board: Environmental and Economic Assessment Tools

This site lists multiple web-based and downloadable tools that can be used for energy analyses.


DEER: Database for Energy Efficient Resource

This database is maintainted by the California Energy Commission and lists resources related to energy use and efficiency. 


Energy Design Resources - CA

Energy design tools are available to be used for free online or available to download.


Building Materials Property Table

This website lists performance characteristics for various envelope materials. 


One Building

This is an online forum of discussion for energy efficiency, computer model software users.


EPA’s Target Finder

Target Finder is a goal-setting tool that informs your design team about their project’s energy performance as compared to a national database of projects compiled by the EPA.


Building Energy Software Tools Directory

This directory provides information on 406 building software tools for evaluating energy efficiency, renewable energy, and sustainability in buildings.


EnergyPlus Format Weather Data Resources

Weather data for more than 2100 locations are available in EnergyPlus weather format.


DOE-2 Format Weather Data Resources

Weather data for U.S. and Non-U.S. locations in BIN format.


BEMbook – Building Energy Modeling Book

A web-based, free content project by IBPSA-USA to develop an online compendium of the domain of Building Energy Modeling (BEM). The intention is to delineate a cohesive body of knowledge for building energy modeling.

Technical Guides

Advanced Buildings Core Performance Guide

A guide for achieving energy efficiency in new commercial buildings, referenced in the LEED energy credits.


ENERGY STAR Building Upgrade Manual

This manual is a strategic guide for planning and implementing energy-saving building upgrades. It provides general methods for reviewing and adjusting system control settings, plus procedures for testing and correcting calibration and operation of system components such as sensors, actuators, and controlled devices.


Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 – Design & Construction

This document is USGBC’s second (v2.0) major release of guidance for district or campus thermal energy in LEED, and is a unified set of guidance comprising the following an update to the original Version 1.0 guidance released May 2008 for LEED v2.x and the initial release of formal guidance for LEED v2009.


COMNET Commercial Buildings Energy Modeling Guidelines and Procedures

This manual offers guidance to building energy modelers, ensuring technically rigorous and credible assessment of energy performance of commercial and multifamily residential buildings. It provides a streamlined process that can be used with various existing modeling software and systems, across a range of programs.


2009 ASHRAE Handbook of Fundamentals, Chapter 19

Chapter 19 is titled, “Energy Estimating and Modeling Methods”. The chapter discusses methods for estimating energy use for two purposes: modeling for building and HVAC system design and associated design optimization (forward modeling), and modeling energy use of existing buildings for establishing baselines and calculating retrofit savings (data-driven modeling).


Treatment of Distric or Campus Thermal Energy in LEED v2 and LEED 2009 (Updated August 13, 2010)

Required reference document for DESDistrict energy system: a central energy conversion plant and transmission and distribution system that provides thermal energy to a group of buildings (e.g., a central cooling plant on a university campus). It does not include central energy systems that provide only electricity. systems in LEED energy credits.

Publications

ANSI/ASHRAE/IESNA Standard 90.1–2007 User’s Manual (ASHRAE).

ASHRAE writes standards for the purpose of establishing consensus for: 1) methods of test for use in commerce and 2) performance criteria for use as facilitators with which to guide the industry.


Energy Information Administration

Energy statistics from the U.S. government.


New Buildings Institute— Advanced Lighting Guidelines: 2003 Edition

This guide includes instructional graphics and superior lighting design solutions for varying types of buildings and spaces, from private offices to big box retail stores.


Building Energy Performance News

This website offers information on energy efficiency in buildings, highlighting success stories, breakthrough technology, and policy updates.


GreenSource magazine

Bimonthly publication on case studies and new technologies for energy efficiency in commercial buildings. 


AIA Local Leaders in Sustainability: Green Incentives

AIA publication highlighting local and state green building incentives.


Federal Research and Devlopment Agenda for Net-Zero Energy, High-Performance Green Buildings

2008 guidelines and performance goals from the National Science and Technology Council.


Energy Design Resources (EDR) Simulation Guidebooks

Information about energy-efficient building practices available in EDR's Design Briefs, Design Guidelines, Case Studies, and Technology Overviews.

Software Tools

Building Energy Software Tools Directory

DOE tools for whole building analyses, including energy simulation, load calculation, renewable energy, retrofit analysis and green buildings tools.


Building and Fire Research Laboratory

This is a computer program that predicts the one-dimensional transfer of heat and moisture.


DesignBuilder and EnergyPlus

DesignBuilder is a Graphical User Interface to EnergyPlus. DesignBuilder is a complete 3-D graphical design modeling and energy use simulation program providing information on building energy consumption, CO2Carbon dioxide emissions, occupant comfort, daylighting effects, ASHRAE 90.1 and LEED compliance, and more.


Integrated Environmental Solutions – Virtual Environment Pro / Apache

IES VE Pro is an integrated computing environment encompassing a wide range of tasks in building design including model building, energy/carbon, solar, light, HVAC, climate, airflow, value/cost and egress.

Advanced Energy Design Guide Checklist

Option 2: Prescriptive Compliance Path

Use this checklist of prescriptive requirements (with sample filled out) to have an at-a-glance picture of AEDG requirements for Option 2, and how your project is meeting them.

Advanced Buildings Core Performance Guide (CPG) Checklist

Option 3

This spreadsheet lists all the requirements for meeting EAp2 – Option 3 and and EAc1 – Option 3. You can review the requirements, assign responsible parties and track status of each requirement through design and construction.

Energy Simulation Narrative

Option 1

Sometimes the energy simulation software being used to demonstrate compliance with Option 1 doesn't allow you to simulate key aspects of the design. In this situation you'll need to write a short sample narrative, as in these examples, describing the situation and how it was handled.

Equipment and Product Cut Sheets

All Options

In your supporting documentation, include spec sheets of equipment described in the Option 1 energy model or Options 2–3 prescriptive paths.

PRM Table

Option 1

This is a sample building energy performance and cost summary using the Performance Rating Method (PRM). Electricity and natural gas use should be broken down by end uses including space heating, space cooling, lights, task lights, ventilation fans, pumps, and domestic hot water, at the least.

Tariff Charges

Option 1

Option 1 calculates savings in annual energy cost, but utility prices may vary over the course of a year. This sample demonstrates how to document varying electricity tariffs.

Modeled Energy Reductions

Option 1

This graph, for an office building design, shows how five overall strategies were implemented to realize energy savings of 30% below an ASHRAE baseline. (From modeling conducted by Synergy Engineering, PLLC.)

U.S. Climate Zones

All Options

The climate zones shown on this Department of Energy map are relevant to all options for this credit.

Appendix G Fan Power Calculator

Option 1

This spreadsheet, provided here by 7group, can be used to calculate the fan volume and fan power for Appendix G models submitted for EAp2/EAc1.  Tabs are included to cover both ASHRAE 90.1-2004 and 90.1-2007 Appendix G methodologies.

LEED Online Forms: NC-2009 EA

Sample LEED Online forms for all rating systems and versions are available on the USGBC website.

Design Submittal

PencilDocumentation for this credit can be part of a Design Phase submittal.

3928 Comments

0
0
SI CHEN
Feb 15 2017
Guest
113 Thumbs Up

v2009_Minimum Energy Performance Calculator_v06

Hi All,

I am working on a LEED NC 2009 project and have questions about filling up the v2009_Minimum Energy Performance Calculator_v06. Hope someone can give me some advice. Thanks.

1) In the 'Air-side HVAC' sheet, there is one parameter called Total heating capacity. I wonder if this number should be the same as the Total boiler capacity in the 'Water-side HVAC', if boiler is the only heat source.

2) Is it acceptable or normal for proposed model to have higher heating capacity than the baseline model? As the designed boiler capacity was oversized a lot.

Thanks.

1
1
0
Marcus Sheffer LEED Fellow, 7group Feb 15 2017 LEEDuser Expert 68625 Thumbs Up

1. That would be the heating capacity for any unitary equipment and the coils in the air side equipment. The boiler capacity would not be expected to match this value, it could be higher of lower.

2.It is not necessarily normal but it could be acceptable. Providing an explanation for these kinds of anomalies is always very helpful to the reviewer.

Post a Reply
0
0
MKK LEED
Feb 13 2017
LEEDuser Member
226 Thumbs Up

Baseline system selection

Project Location: United States

I have a building that is roughly 20,000ft2 of office, plus another 13,000ft2 of underground parking that is heated to 50F. Should I include the parking in the area and use System 5 for my baseline, or exclude it and use system 3? I typically would say exclude parking area, just account for the lights and fan energy, but since it is heated I lean to including it. Excluding it obviously makes the EUI very strange since you are heating it, but more importantly the baseline system changes. Has anyone seen this before? Any advice?

1
1
0
Marcus Sheffer LEED Fellow, 7group Feb 13 2017 LEEDuser Expert 68625 Thumbs Up

All conditioned space would be included in the selection of the baseline system type.

Post a Reply
0
0
SI CHEN
Feb 13 2017
Guest
113 Thumbs Up

Baseline 4 Orientations or Not

Hi All,

I am working on a LEED NC 2009 Project. I just wonder if I need to use the average results for 4 orientations for baseline model. Is it acceptable to only run 0 degree baseline model? Where can I find the requirements on such issues? Many thanks in advance!

1
2
0
R2M Solution Srl R2M Solution Srl Feb 13 2017 LEEDuser Member 209 Thumbs Up

You don't rotate it if it is an existing building or if you can demonstrate that a different orientation would be impossible.

2
2
0
Marcus Sheffer LEED Fellow, 7group Feb 13 2017 LEEDuser Expert 68625 Thumbs Up

There is a reference to this in the Advanced Energy Modeling Guide for LEED. Existing building clearly do not need to be rotated. Existing/addition combinations do not get rotated if the addition is less than 50% of the existing. It gets a little fuzzy if the addition is greater than 50%. If you look at ASHRAE 90.1-2010 there are two exceptions listed which include situations where there is little difference between the glazing areas of each side of the building and where physical constraints of the site make rotation impractical. I think you could cite those as rational reasons not to rotate.

Post a Reply
0
0
Vassil Vassilev Manager Termoservice OOD
Feb 12 2017
LEEDuser Member
424 Thumbs Up

ASHRAE 90.1-2007, 6.5.3.1.1,exception b

Project Location: Bulgaria

Greetings,
According to ASHRAE 90.1-2007, 6.5.3.1.1,exception b, individual exhaust fans with motor nameplate kW of 0.75 kW or less could be excluded when estimating Fan system power limitation.
There are projects however, where there are such small fans, but they are part of some systems - say small 100% OA supply AHUs with only a supply fan and the small fans are the exhaust part of these systems.
The question is:
Should the power of these small fans (exception b) in the above cases be excluded (taken off) from the fan power calculation performed by the simulation software, or with other words, shall we enter these small fans in the energy model?
Thanks.

1
2
0
Marcus Sheffer LEED Fellow, 7group Feb 12 2017 LEEDuser Expert 68625 Thumbs Up

The Proposed is always modeled as designed.

The baseline fans are modeled according to G3.1.2.9. If a fan is part of the HVAC system then it is covered. If a fan is not part of the HVAC system then it is not regulated and considered a process load. The size of the fan does not matter.

That exception would apply for code compliance - those small fans do not have to comply with this prescriptive requirement.

2
2
0
Vassil Vassilev Manager, Termoservice OOD Feb 13 2017 LEEDuser Member 424 Thumbs Up

Thanks Marcus,
It was very useful explanation.

Post a Reply
0
0
Ahmed Labeeb Egypt Dar Al-Handasah
Feb 09 2017
LEEDuser Member
2 Thumbs Up

Baseline Pumping Power

Project Location: United Arab Emirates

Based on ASHRAE 90.1, the chilled water pumping power must be 22 W/gpm and does not mentioned the effect of pumping head. the majority of projects that I am working on them, the proposed pumping power is higher than 22 W/gpm because of the head.

How can I solve this issue or how can I design the baseline chilled water pumps based on flow and head?

1
1
0
Ahmed Labeeb Egypt, Dar Al-Handasah Feb 09 2017 LEEDuser Member 2 Thumbs Up

Sorry a repeated post.

Post a Reply
0
0
Ahmed Labeeb Egypt Dar Al-Handasah
Feb 09 2017
LEEDuser Member
2 Thumbs Up

Baseline Pumping Power

Project Location: United Arab Emirates

Based on ASHRAE 90.1, the chilled water pumping power must be 22 W/gpm and does not mentioned the effect of pumping head. the majority of projects that I am working on them, the proposed pumping power is higher than 22 W/gpm because of the head.

How can I solve this issue or how can I design the baseline chilled water pumps based on flow and head?

1
1
0
Ahmed Labeeb Egypt, Dar Al-Handasah Feb 09 2017 LEEDuser Member 2 Thumbs Up

Sorry a repeated post.

Post a Reply
0
0
Ahmed Labeeb Egypt Dar Al-Handasah
Feb 09 2017
LEEDuser Member
2 Thumbs Up

Baseline Pumping Power

Project Location: United Arab Emirates

Based on ASHRAE 90.1, the chilled water pumping power must be 22 W/gpm and does not mention the effect of pumps' head. the majority of projects that I am working on them, the proposed pumping power is higher than 22 W/gpm because of the pumps' head.

How can I solve this issue or how can I design the baseline chilled water pumps based on flow and head?

1
6
0
Marcus Sheffer LEED Fellow, 7group Feb 09 2017 LEEDuser Expert 68625 Thumbs Up

The baseline must be 22 W/gpm of collective chilled water pump power (both primary and secondary). The loop is auto-sized which determines the gpm needed.

I can't really say how to solve the pump issue in your designs that produces greater power demands than the baseline. It is unusual that you would have this issue because most projects show a savings against the baseline.

2
6
0
Ahmed Labeeb Egypt, Dar Al-Handasah Feb 10 2017 LEEDuser Member 2 Thumbs Up

Based on ASHRAE 2004 User Manual, the baseline pumping power is calculated based on a pumping head = 75 foot and efficiency = 60%.

Consequently, Should I redesign the proposed pumping power based on head = 75 ft and Eff = 60% and the only difference will be the chilled water flow to make the comparison apples to apples.

3
6
0
Ahmed Labeeb Egypt, Dar Al-Handasah Feb 10 2017 LEEDuser Member 2 Thumbs Up

Based on ASHRAE 2004 User Manual, the baseline pumping power is calculated based on a pumping head = 75 foot and efficiency = 60%.

Consequently, Should I redesign the proposed pumping power based on head = 75 ft and Eff = 60% and the only difference will be the chilled water flow to make the comparison apples to apples.

4
6
0
Marcus Sheffer LEED Fellow, 7group Feb 10 2017 LEEDuser Expert 68625 Thumbs Up

No. The Proposed must be modeled as designed and the Baseline loop is auto-sized.

5
6
0
Aru Sau Feb 10 2017 Guest 108 Thumbs Up

Correct me if I am wrong - I would convert the 75' head to pressure and calculate the gpm of the proposed system. I.e. if you have 1000 gpm, 100' head & 40 hp pump. For the sake of LEED proposed, I would put calculated w/gpm value considering it on 75' head. That way it could be apple to apple not apple to orange.

6
6
0
Marcus Sheffer LEED Fellow, 7group Feb 10 2017 LEEDuser Expert 68625 Thumbs Up

The proposed loop would be modeled as designed. The proposed pump is sized based on the head and the flow needed to serve the coiling coils in the Proposed design.

The 75' head is what was used to come up with the 22W/gpm in the baseline, it is not a value you should use in the models at all. The baseline pump size would be determined by auto-sizing the loop and using the required W/gpm. This will provide you with the necessary flow to serve the coils to meet the load.

It seems as if you are trying to design the baseline system which is a common tendency for mechanical designers. It is not designed. In some cases as it is modeled would not actually function in reality. It must function in the computer simulation, not in real life.

In many cases you don't want this to be apples to apples because the system configuration can vary and this should be taken into account.

Post a Reply
0
0
John Covello LEED AP BD+C, EBOM, LEED and Sustainability Manager Development Management Group
Feb 08 2017
LEEDuser Member
771 Thumbs Up

Walk in Freezer Auto Light Shut off

Project Location: Thailand

Hello Everyone,

Our resort project has 25 walk in freezers for food storage. After an inquiry I have a ruling stating that a door control sensor is not acceptable as an auto shut off mechanism under ASHRAE 90.1-2007 9.4.1.1. The light is set to shut off 7seconds after it closes in the current design. An occupancy sensor was suggested. Is anyone aware of other options that might fit the requirement for 9. 4.1.1?

Thanks for your help.

1
3
0
Marcus Sheffer LEED Fellow, 7group Feb 09 2017 LEEDuser Expert 68625 Thumbs Up

A ruling from whom?

When people enter the cooler does the door stay open while they get (or put in) what they need and then leave? If so I would argue that your door sensor qualifies under 9.4.1.1 (c). It would probably save more energy than a motion sensor since the sensors typically have a longer delay.

2
3
0
Jean Marais b.i.g. Bechtold DesignBuilder Expert Feb 09 2017 LEEDuser Member 10950 Thumbs Up

It should be considered that that the lighting type matters here. LEDs don't use the same start up currents and energy usage than T5 lights, for example and better sustain on off cycles.

Another problem is that walkin coolers' doors are often self closing, so a light that goes out when the person is still inside (because the door swings closed behind him) is not a good design. This would lead to users jambing the door open while they are in there, wasting the cooling energy.

An infra-red occupancy sensor should be robust enough, right?

3
3
0
John Covello LEED AP BD+C, EBOM, LEED and Sustainability Manager, Development Management Group Feb 14 2017 LEEDuser Member 771 Thumbs Up

Hi Marcus & Jean,

Thanks for your feedback.

I got my interpetation from ASHRAE on a Request for Interpetatiopn form. I has hoping someone had dealt with this before and might have heard of other alternatives than occupancy sensor. The ASHRAE Interpetation states:

Background: Our project is using door sensors for lighting controls for Walk in Freezers and Room Chillers. Do these qualify as an occupant sensor (Section 9.4.1.1b)? They would turn the light on when someone is inside, and turn off the light when it is closed. No one will be inside with a closed door.
Interpretation: A door operated sensor for a freezer room counts as an occupant sensor for Section 9.4.1.1b of ASHRAE/IESNA Standard 90.1.
Question: Is this interpretation correct?
Answer: No
Comments: A door sensor (switch) does not meet the intent or specific language/definition in the standard because it only senses whether the door is open or closed and not whether the room is occupied or vacant.

Also this comment from ASHRAE rep:

In a chiller space – such as a walk-in freezer – there needs to be an occupancy sensor or timer to control the lighting. The fact that it’s not regularly occupied highlights the reason for it.
Say someone leaves the lights on when they walk out of the freezer. If it’s unoccupied for 176 hours until the next person walks in, the lights will have been on the entire time.
Preventing that sort of un-needed illumination is why the requirement is written the way it’s written.
So the example of “no one will be inside with a closed door” isn’t always true. If there’s mechanisms to allow people to exit, then there must be times when people are in a freezer with the door closed.

We are looking into specialized occupancy sensors for freezers. There are some available on the market.

Post a Reply
0
0
Vassil Vassilev Manager Termoservice OOD
Feb 07 2017
LEEDuser Member
424 Thumbs Up

Misc. loads entry in the simulation software

Project Location: Bulgaria

Greetings,
Regarding Misc. load entry in the simulation software, there is a following query:
As required (talking for electrical loads only), we are entering the value which is to be used for cooling/heating load estimation.
There are el. loads like for electric heaters, hair dryers, etc, where the heating load in the room coincides with those on their nameplates, but we are not referring them now.
In some cases however, the electrical loads are different from the load listed in the equipment nameplate. Like for office equipment, open electric motors, etc. For example, the office equipment load is somehow between 10 - 17 % from those of the name plate. The similar situations is with open el. motors - their heat load delivered in the room is about 18% of the nameplate load. The electrical designers however are designing the electrical network and power supply based on the nameplate data.
The question is (example): There is office equipment with 200 W nameplate and power supply sized to cover this load. The heat delivered in the room is about 20-30 W, which are entered in the software. How should be proceeded with the remaining el. power (170-180 W) - shall we enter it as some process load which doesn't affect cooling/heating balance of the HVAC systems, or…..?
Thanks.

1
2
0
Marcus Sheffer LEED Fellow, 7group Feb 07 2017 LEEDuser Expert 68625 Thumbs Up

You ignore the remaining "power". If it never comes on it does not have a schedule. The electrical engineer has to size the electrical system to accommodate greater than actual loads so you never use the full capacity of the system. Use the actual loads in the space and forget the rest.

2
2
0
Vassil Vassilev Manager, Termoservice OOD Feb 07 2017 LEEDuser Member 424 Thumbs Up

Thanks Marcus,
Efficient as always

Post a Reply
0
0
Gustavo De las Heras Izquierdo Arch. Eng. LEED AP BD+C; O+M; CxA: Green Rater in Training Revitaliza Consultores
Jan 27 2017
Guest
2308 Thumbs Up

Requirements for instant water heater with no storage tank

Project Location: Mexico

Hallo,

I have read the insulation requirements in Section 7.4.3 but it seems to focus on circulating and non-circulating systems with a storage tank.

Does anyone know insulation and heat traps requirements for piping in instant water heater systems with NO storage tank?

Thanks!

1
1
0
Marcus Sheffer LEED Fellow, 7group Jan 29 2017 LEEDuser Expert 68625 Thumbs Up

It would make sense that there are no pipe insulation requirements for pipes from an instantaneous water heater. Same with heat traps (nothing to trap).

Post a Reply
0
0
Billy Condor Engineer
Jan 26 2017
Guest
14 Thumbs Up

Vertical fenestration for Proposed Case

Project Location: Peru

Hello,

I'm evaluating the energy efficiency of a building that has almost 100% of curtainwall, however the architect says that his project has high beams height (the ones attached to the exterior envelope), and therefore, the WWR shouldn't really be almost 100% but much more less.
So my question is, for calculating the WWR (and simulate this on the energy model too), do I have to take away the area from the beams attached to the envelope?

Many thanks!

1
3
0
Marcus Sheffer LEED Fellow, 7group Jan 26 2017 LEEDuser Expert 68625 Thumbs Up

If the curtainwall cover this and the glazing is opaque, like a spandrel panel, then it is a wall and not fenestration. If the glazing over this lets light in then it is window. If there is no glazing over the beam then it is a wall.

2
3
0
Billy Condor Engineer Jan 27 2017 Guest 14 Thumbs Up

Thanks for your response Marcus.

The curtainwall covers the beams, the glazing will be clear (minimum VLT 0.55) and there won't be spandrel panels. As curtainwall covers the beams, glazing doesn't permit light in in this area with beams (of course there are intermediate portions of glazing with no beams behind, where light in).
Therefore, to have it clear, I think I should deduct beams area from the whole curtainwall area, please confirm.

Thanks in advance!

3
3
0
Marcus Sheffer LEED Fellow, 7group Jan 27 2017 LEEDuser Expert 68625 Thumbs Up

It is still hard to say. The way to justify this is to examine the definitions of fenestration and wall. The slab edge is clearly a wall. The beams may or may not be a wall. If that area lets light or solar radiation inside then I think it is fenestration. Look at the vertical fenestration definition and maybe you can justify it as not fenestration if the configuration is at all similar to the trombe wall mentioned. Dive into the definitions and see what you can justify.

Post a Reply
0
0
jorge torres coto Building Systems Commissioning Engineer Empirical Engineering, LLC
Jan 25 2017
LEEDuser Member
637 Thumbs Up

MANDATORY REQUIREMENTS AHSRAE 90.1

Does anyone know if isolation valves on a multiple chiller plant are required by ASHRAE, or they simply best practice?
I have looked into this in ASHRAE documents, but have not found anything yet. I do know for a fact that a non-operating chiller will pass water without cooling it and eventually mix with the cooled water leaving the operating chiller producing a mixed chilled water temperature that will be higher than setpoint to the load (proportional to the flows of each chiller).
I obviously get resistance from the installing contractors due to monetary issues.
Thanks
Jorge

1
1
0
Jean Marais b.i.g. Bechtold DesignBuilder Expert Jan 26 2017 LEEDuser Member 10950 Thumbs Up

I can't remember any requirements.

The installers should install equipment according to plan. The MEP and Controls planners should have planned everything properly. If a mixed temperature is part of the design, then don't mess with the design as it could have unforseen consequenses. The best practise is to check with the design team if it is an oversight or not. Installing firms are always trying to cut corners to save money and then if anything goes wrong it's the fault of the designers. If it's a design issue or a cost issue, is impossible to say. Perhaps the same investment can save more energy if invested elsewhere.

If it is an oversight, then it would have an impact on the overall control of the system and everyone will be happy you picked up on it.

Post a Reply
0
0
SI CHEN
Jan 22 2017
Guest
113 Thumbs Up

v2009_Minimum Energy Performance Calculator_v6

Hi All,

I am working on a project with VRF system for a LEED 2009 certification. When I filled up the excel sheet of Minimum Energy Performance Calculator, I found that there is one page of water side system. However, for VRF system, there is on chiller or chiller water. So how shall I fill up that page? Can I leave it blank?

My baseline system is Sys 4- packaged single-zone heat pumpA type of heating and/or cooling equipment that draws heat into a building from outside and, during the cooling season, ejects heat from the building to the outside. Heat pumps are vapor-compression refrigeration systems whose indoor/outdoor coils are used reversibly as condensers or evaporators, depending on the need for heating or cooling. In the 2003 CBECS, specific information was collected on whether the heat pump system was a packaged unit, residential-type split system, or individual room heat pump, and whether the heat pump was air source, ground source, or water source. (DX Cooling and air-to-air heat pump).

Many thanks!

1
1
0
Marcus Sheffer LEED Fellow, 7group Jan 22 2017 LEEDuser Expert 68625 Thumbs Up

Sounds like you have no water-side equipment in your models so leave it blank.

Post a Reply
0
0
Vassil Vassilev Manager Termoservice OOD
Jan 19 2017
LEEDuser Member
424 Thumbs Up

Minimum Energy performance Calculator

Project Location: Russian Federation

Greetings,
We have a project, which is registered upon LEED-NC v2009, with unit type SI.
The online form of EAp2 has a new form, which is directing us to upload the Minimum Energy Performance Calculator. This calculator however is for LEEDv4 and if used for LEED 2009, it is to use the ASHRAE 90.1-2010 pathway.
The designers have already been informed that they should refer ASHRAE 90.1-2007and the project design is completed.
Please advice how to proceed in this case.
Thanks

1
1
0
Marcus Sheffer LEED Fellow, 7group Jan 19 2017 LEEDuser Expert 68625 Thumbs Up

There is a version of the MEPC that is based mostly on 90.1-2007.

You have a few choices.

1. You can use the new form with the MEPC. It has SI units as an option so that helps you but it still has some quirks and issues.
2. You can contact GBCIThe Green Building Certification Institute (GBCI) manages Leadership in Energy and Environmental Design (LEED) building certification and professional accreditation processes. It was established in 2008 with support from the U.S. Green Building Council (USGBC). and request that they replace the form in LEED Online with the older v5 form and then use the previous Section 1.4 Tables.
3. You can simply upload the v5 version of the form and the Section 1.4 Tables, however this will not record information correctly in LEED Online and may affect the calculations and documentation of other related credits.

The one thing you definitely should not do is use the new form with the old Section 1.4 Tables. This combination will not provide the reviewer with the information they need to evaluate EAp2.

Post a Reply
0
0
SI CHEN
Jan 18 2017
Guest
113 Thumbs Up

Baseline Air Flow Rate

Hi All,

According the ASHRAE standards, I used system 10 - Heating only and Ventilation for the baseline model. However, the autosized supply air flow rate (based on supply air T=40 degree) is much higher than the designed flow rate. As a result, the project can get a very good energy and cost savings. But I am unsure if this is the normal case for energy modelling. Thanks in advance!

1
1
0
Marcus Sheffer LEED Fellow, 7group Jan 19 2017 LEEDuser Expert 68625 Thumbs Up

Baseline system air flow rates for System Types 9 and 10 shall be determined based on the temperature differential between 105 degrees F and the design space heating temperature setpoint, the minimum outdoor air flow rate, or the air flow rate required to meet applicable code or accreditation standards, whichever is greater. You usually do not see a significant savings related to these heating only systems.

Post a Reply
0
0
Vassil Vassilev Manager Termoservice OOD
Jan 18 2017
LEEDuser Member
424 Thumbs Up

Table 6.8.1 for air cooled liquid chillers

Project Location: Bulgaria

Greetings,
In the project we are modeling, on the plant level there are selected Air cooled chilled water chillers, which are also arranged to operate as Heat PumpA type of heating and/or cooling equipment that draws heat into a building from outside and, during the cooling season, ejects heat from the building to the outside. Heat pumps are vapor-compression refrigeration systems whose indoor/outdoor coils are used reversibly as condensers or evaporators, depending on the need for heating or cooling. In the 2003 CBECS, specific information was collected on whether the heat pump system was a packaged unit, residential-type split system, or individual room heat pump, and whether the heat pump was air source, ground source, or water source. water heating package (using the title of AHRI 550/590).
In the Standard 90.1 there is a table 6.8.1.C, which covers the chiled water or cooling mode of operation's COP.
The question is: what value should we refer to when looking for compliance with the project's COP for heating mode?
Thanks.

1
1
0
Marcus Sheffer LEED Fellow, 7group Jan 18 2017 LEEDuser Expert 68625 Thumbs Up

Some of these types of systems are not covered by any of the 6.8.1 tables. If it is not covered then there is no minimum efficiency required.

Post a Reply
0
0
Aru Sau
Jan 17 2017
Guest
108 Thumbs Up

Trace 700 Performance Summary Report

Project Location: United States

Is the Performance Summary Report generated by Trane Trace 700 (Ver 3.0) be enough for the LEED V4 EA credit?
Do I have to still fill out the "v4_Minimum Energy Performance Calculator_August_23_2016.xlsm" ?
Is there any standard energy simulation report format available?

1
1
0
Marcus Sheffer LEED Fellow, 7group Jan 18 2017 LEEDuser Expert 68625 Thumbs Up

No that report will not be enough.

Yes you have to fill out the MEPC. Use it to make sure you have modeled the baseline correctly.

I am not aware of a standard format.

For Trace I would also upload the LEED Summary, Equipment Energy Consumption, System Entered Values, Space Entered Values, and Plant Entered Values reports.

Post a Reply
0
0
Charalampos Giannikopoulos Senior Sustainability Consultant DCarbon
Jan 16 2017
LEEDuser Member
1761 Thumbs Up

G3.1.1. Additional system types for nonpredominant conditions

We’ve got a comment for a hotel project that “secondary HVAC systems should be specified in the Baseline building if any of the exception(s) from G3.1.1 are applicable. The non-residential portion of the building appears to be greater than 20,000 square feet and some of the areas of the building are on a different schedule than the hotel.”
In that case, where the project may fall under case (a) of G3.1.1, which system type should the additional system types for non-predominant conditions conform to? Thank you!

1
6
0
Marcus Sheffer LEED Fellow, 7group Jan 16 2017 LEEDuser Expert 68625 Thumbs Up

Subtract the residential area (hotel) from the total area. Use the remaining area to reenter Table G3.1.1A.

2
6
0
Charalampos Giannikopoulos Senior Sustainability Consultant, DCarbon Jan 25 2017 LEEDuser Member 1761 Thumbs Up

Thank you Marcus. However, our hotel building consists of 12 floors (in total, including the residential uses) and apparently non-residential spaces are less that 25,000 sf. (including three different types - mechanical, offices, restaurants). According to table G3.1.1A should we select our additional system based on area only or consider the amount of floors as well? On the one hand we should use System 4 (which would make sense) and on the on the other we should use System 8 which is very complicated for spaces of insignificant size.

3
6
0
Marcus Sheffer LEED Fellow, 7group Jan 25 2017 LEEDuser Expert 68625 Thumbs Up

If you subtract off the residential floors then how many are left?

4
6
0
Charalampos Giannikopoulos Senior Sustainability Consultant, DCarbon Jan 25 2017 LEEDuser Member 1761 Thumbs Up

4 floors are left!

5
6
0
Marcus Sheffer LEED Fellow, 7group Jan 25 2017 LEEDuser Expert 68625 Thumbs Up

So it looks like a system #6.

6
6
0
Charalampos Giannikopoulos Senior Sustainability Consultant, DCarbon Feb 02 2017 LEEDuser Member 1761 Thumbs Up

Thanks Marcus!

Post a Reply
0
0
Nicole Isle Chief Sustainability Strategist Glumac
Jan 13 2017
LEEDuser Member
35 Thumbs Up

Garage Exhaust CO Monitoring Savings

Project Location: United States

Per CIRCredit Interpretation Ruling. Used by design team members experiencing difficulties in the application of a LEED prerequisite or credit to a project. Typically, difficulties arise when specific issues are not directly addressed by LEED information/guide 10371, we are allowed to claims savings for garage exhaust CO monitoring if we can demonstrate that it's not common practice. I am able to demonstrate that, but my question is how do we calculate those savings? In the past I have used a graph from the ASHRAE Applications Handbook which has three different occupany profiles and estimates savings for each profile. This project is a large mixed-use with office, residential, and a mall. According to the Applications graphs, this type of facility should see about 20% savings with variable speed control. However, the handbook states that this assumes either two-speed control or variable-pitch blades, both of which are much less efficient than VFDA variable frequency drive (VFD) is a device for for controlling the speed of a motor by controlling the frequency of the electrical power supplied to it. VFDs may be used to improve the efficiency of mechanical systems as well as comfort, because they use only as much power as needed, and can be adjusted continuously.. I think a more accurate way to calculate the actual savings is to take the percentages of the profile (ie 60% at 11am and 70% at 3pm) and apply the fan laws to calculate the BHP of the fans for each hour of the day. For example, the BHP at 11am would be 22% of the peak BHP. To be conservative I could use 2.2 as the fan law exponent, which has been approved by local utilities for incentives on previous projects. Thus an hourly calc can be performed and the annual usage can be tabulated. Has anyone tried this approach or a similar one?

1
1
0
Marcus Sheffer LEED Fellow, 7group Jan 18 2017 LEEDuser Expert 68625 Thumbs Up

Your approach seems reasonable to me. Some additional guidance below.

a. Baseline case shall meet the requirements of ASHRAE 90.1-2010, Section 6.4.3.4.5 Enclosed Parking Garage Ventilation. Baseline fan volume shall be based on the minimum required ASHRAE 62.1 parking ventilation rates of 0.75 cfm/square foot. Baseline system fan power shall be calculated at 0.3 watts per CFM.

b. Proposed case shall reflect the actual design. Evidence shall be provided documenting that demand control ventilation strategies are sufficient to automatically detect contaminant levels of concern in parking garages (Carbon Monoxide, Particulates, VOCs, etc. and NO2) and modulate airflow such that contaminant levels are maintained below specified contaminant concentration as identified in ASHRAE 62.1-2010 Addendum d. Evidence shall also be provided that contaminant sensors are placed in space in an appropriate manner for detection of contaminant in question and that the sensors be calibrated yearly.

c. If other activities occur in the garage area, the ventilation for these uses shall be in addition to garage vehicle ventilation.

d. Proposed case shall be modeled such that a minimum air flow of 0.05 cfm/square foot is maintained.

e. A narrative shall describe all Baseline and Proposed case assumptions included for this measure, and the calculation methodology used to determine the projected savings. The narrative and energy savings should be reported separately from the other efficiency measures in the LEED Form.

f. No more than a 75% fan energy savings shall be claimed for this measure.

Post a Reply
0
0
David Hubka Director - Operations Transwestern Sustainability Services
Jan 13 2017
LEEDuser Expert
3870 Thumbs Up

Manufacturing - prorate energy model

Hello Marcus,

Projects pursuing CS certification are allowed to prorate the model based on owner control. Why would they not have a similar path for manufacturing facilities pursuing NC certification?

For example, the "widget maker" consumes 70% of the building's total energy hence the modeler would be able to prorate the model as if 70% were outside the control of the owner.

thank you for any insight you can provide.

1
1
0
Marcus Sheffer LEED Fellow, 7group Jan 13 2017 LEEDuser Expert 68625 Thumbs Up

CS projects are split between the owner and tenant. It is the fundamental issue of control that makes the difference. If the widget maker builds a building then they control all of the energy use including the process loads and can make decisions that will reduce energy use of that process.

The owner control method for CS was a compromise which was allowed to enable CS projects to ramp up their energy savings over time. In v4 this adjustment went away.

Post a Reply
0
0
SI CHEN
Jan 12 2017
Guest
113 Thumbs Up

Perimeter Zones Requirements for Warehouse

Hi All,

I am working on a large warehouse project, which is an open space with the area of 10,000 square meter. This project is targeting at LEED 2009. As the space is quite big, I just wonder if there are any requirements on creating perimeter zones or not. If treating it as one zone, will it influence the energy results? Has anybody have any experience on this? Many thanks in advance!

Alice

1
8
0
Jean Marais b.i.g. Bechtold DesignBuilder Expert Jan 12 2017 LEEDuser Member 10950 Thumbs Up

The baseline must be modelled as per ASHRAE 90.1-2007 app. G. Therein it tells you how to divide the perimeter into virtual zones. You should do this for the proposed model as well as it is good practice (most of the time, there could be situations where it is not depending on the radiation infall from outdoors). As a good rule of thumb...whereever there is a thermostat, model the zone that thermostat is suposed to control. Again, check the standard...there are some good tips in there.

2
8
0
SI CHEN Jan 12 2017 Guest 113 Thumbs Up

Hi Jean,

Thanks for your reply. I read the Table G3.1.7. To my understanding, the HVAC zones have been designed. There are four fan coil heaters distributed in the warehouse. Each air hear has a thermostat. However, I still wonder if it is required to divide the space into four zones as all the internal loads, system etc is the same throughout the warehouse. Many thanks.

3
8
0
Jean Marais b.i.g. Bechtold DesignBuilder Expert Jan 12 2017 LEEDuser Member 10950 Thumbs Up

To be honest, this is a modelling issue. The thing is that a zone is considered "well mixed" in most programs and does not take into account temperature variation across the zone as would occure in real life. To make sure the thermostats and systems respond "semi-realistically" it is usually a good idea to seperate these as suggested. However, it is situational and geometry together with air movement, both thermally induced and mechanically induced are really what should influence your judgement calls.

Does that make sense?

4
8
0
Marcus Sheffer LEED Fellow, 7group Jan 12 2017 LEEDuser Expert 68625 Thumbs Up

In a warehouse you would not typically see any perimeter zoning except maybe by the loading docks. All things being equal in each of the 4 areas you could probably combine them into one thermal block without much of an impact on energy use. Combining areas into fewer thermal blocks in my experience is typically done to simplify the model. As Jean suggests this is a judgement call on the part of the modeler. Like all judgement calls you should be able to defend the actions you take as thermodynamically similar enough to only minimally affect the energy use.

5
8
0
Jean Marais b.i.g. Bechtold DesignBuilder Expert Jan 13 2017 LEEDuser Member 10950 Thumbs Up

I agree and would point out that Marcus says "loading docks", but basically think of other "zones" that may experience other dissimilar thermal loading as well.

For example near a fully glazed wall or near a hot machine. The type of thermostat may also be a consideration. I'm in Europe and just this minute there's a project where we use radiative ceiling elements for heating combined with operative temperature thermostates. Here I would think about hot or cold radiative surfaces as well which may influence the thermostat and drive the heating surface temperatures of the radiative panels. In that case adding additional "virtual" surface to split zones may even negatively effect the thermostat reading, so I need to be careful. At the same time, large spaces (especially high ones) could show some stratification. My software can handle this by using a "non-well mixed" room air model to capture some of these effects without splitting the zone. I've not started this job, but these would be some of the thoughts that would go through my mind to consider.

These kind of impacts start really mattering if the systems are ramping up and down and negatively effect efficiencies which is especially prevelant in radiant systems. Air systems tend to "well mix" better and not suffer from these control symtoms as much.

6
8
0
SI CHEN Jan 13 2017 Guest 113 Thumbs Up

Hi All,

Thanks for your reply.

This warehouse has very few windows. And I already created separate thermal block for loading bays. I just wonder if it is right to treat the whole open-plan warehouse as one zone and adding the flow rates from each air heater together in the ApacheHVAC.

Yes I understand that stratification may occur in the large space. But just wonder if it is necessary to do separate thermal blocks in this case to be in compliance with LEED requirements. Many thanks!

7
8
0
Marcus Sheffer LEED Fellow, 7group Jan 13 2017 LEEDuser Expert 68625 Thumbs Up

For LEED Table G3.1-7 tells you what you have to do. The exception for combining blocks will need to apply in order to combine zones into a single block. If all of the exception criteria apply then you can combine them. Jean has been trying to let you know the thinking that needs to go behind the combining of multiple zones into a single block.

8
8
0
Cory Duggin Energy Project Engineer, TLC Engineering for Architecture Jan 13 2017 LEEDuser Member 161 Thumbs Up

I would divide the large open space into core and perimeter zones at a minimum. Since the the spaces are open to one another, I would make the partitions to be 100% hole.

Post a Reply
0
0
Olaf Dybinski Olaff Energy Solutions
Jan 11 2017
Guest

Which ASHRAE & LEED should I base my simulation on?

Project Location: Poland

Hello, I have a problem with choosing a basis for my simulation.
I have a building that was designed in 2015 and is about to be build. I need to perform simulations for "Optimize Energy performance" credit...
In LEED 2009 it's said the baseline building should be prepared according to Appendix G Standard 90.1-2007. But there were later also versions 90.1-2010 and 90.1-2013 (The building was designed in 2015!)
Should I then follow direct instructions in manual and prepare baseline model according to 90.1-2007 or rather 90.1-2013, because this is the most appropriate for my building?
Please let me know, in case contact via my mail olafdybinski@gmail.com
I would be very thankful for your answers.
Best regards,
Olaf

1
2
0
Marcus Sheffer LEED Fellow, 7group Jan 11 2017 LEEDuser Expert 68625 Thumbs Up

The baseline is determined by the version of LEED you register under, not the local code or the year it was designed.

If the project is registered under LEED 2009 then you use 90.1-2007. You can also use 90.1-2010 and there is a alternative point threshold if you do so published in a LEED InterpretationLEED Interpretations are official answers to technical inquiries about implementing LEED on a project. They help people understand how their projects can meet LEED requirements and provide clarity on existing options. LEED Interpretations are to be used by any project certifying under an applicable rating system. All project teams are required to adhere to all LEED Interpretations posted before their registration date. This also applies to other addenda. Adherence to rulings posted after a project registers is optional, but strongly encouraged. LEED Interpretations are published in a searchable database at usgbc.org.. If registered under LEED v4 you use 90.1-2010. I have not yet seen anything about using 90.1-2013.

2
2
0
Olaf Dybinski Olaff Energy Solutions Jan 12 2017 Guest

Thank you very much Marcus!

Post a Reply
0
0
sherif el adly Egis Rail
Jan 10 2017
LEEDuser Member
54 Thumbs Up

Innovative ideas

Dear All,

In my project I am trying to reduce energy consumption, I am using LED lights, high efficient air cooled units (baseline is water cooled chillers).
The building already is underground building but still I can't achieve the required reduction in energy.
Is there an innovative idea which can significantly reduce the energy.
The client is rejecting the use of water cooled chillers.

Thanks

Start a new LEED comment thread

Feb 21 2017
Type the characters you see in this picture. (verify using audio)
Type the characters you see in the picture above; if you can't read them, submit the form and a new image will be generated. Not case sensitive.

Copyright 2017 – BuildingGreen, Inc.