Upgrade to LEED 2009? How to Choose for Your Project

Content Scope: 
Use Tabbed Form
Bird's Eye view

LEED 2009 launched

USGBC launched the new LEED 2009 rating systems (NC, Schools, CS, EBOMEBOM is an acronym for Existing Buildings: Operations & Maintenance, one of the LEED 2009 rating sytems., CI) in April 2009 as part of its LEED version 3 initiative. Thousands of LEED-hopeful projects, however, were previously registered (or continued to register until the June 26, 2009 deadline) for the earlier version of the applicable rating system—mostly LEED for New Construction v2.2.

Although projects registered prior to the LEED 2009 rollout are under no obligation to switch to LEED 2009, USGBC has been encouraging them to do so. Among other things, USGBC allowed projects to transfer into the appropriate LEED 2009 rating system at no additional charge until December 31, 2009.

Should your project consider switching?

Switching to LEED 2009 offers:

  • A system in which the technical basis and credit weighting have been evaluated in a more scientific manner, which has resulted in some LEED categories having more importance, and others less, than in previous versions.
  • The potential of up to four bonus points for RPc1: Regional Priority.
  • Use of the most up-to-date industry standards such as ASHRAE 90.1-2007.
  • Use of improved templates (now called “credit forms”), the new LEED Online 3 system with better technical support, and a streamlined certification review process. 
  • Expanded and improved Reference Guides.  
  • Fewer credit interpretation rulings (CIRs) to keep track of, because many previous CIRs have been inserted directly into the new credit requirements. New CIRs will be managed differently, as “errata” to the rating system. 
  • Many similarities with LEED v2.2. Even with all these improvements, the requirements for the majority of credits have not changed substantially, so you can take most of your existing LEED work on a project with you.

Why would a project want to stay with pre-2009 systems like LEED-NC v.2.2?

  • Rely on your design team’s knowledge of the old, familiar system and the already-determined certification goals and expectations for each responsible party.
  • Avoid the new Minimum Program Requirements (MPRs), which include a minimum building size of 1,000 square feet, and mandatory sharing of whole-building energy and water data.
  • Although a project might not yet have begun the certification process under the older rating system, lots of preparatory work may have been completed, and consulting fees spent.
  • Avoid having to reevaluate against newer standards for certain credits. EAc1: Optimize Energy Performance, in particular, needs to be reevaluated against the upgraded ASHRAE 90.1-2007 guidelines, which may involve a new round of energy modeling. In California, EAc1 can still be evaluated against Title-24-2005, but doing so creates version issues and may require additional modeling to prove compliance.
  • More on this below, but you might be able to achieve a higher certification level (such as Gold versus Silver) by staying with a pre-2009 system. Usually, the system under which a project is certified is not as important to the owner and the public as the certification level. 

There are good arguments on either side of switching. Your decision will probably be tipped in one direction or the other by your project specifics. Now, on to the numbers.

Recalibration and credit weighting

All LEED 2009 rating systems use a basic 100-point scale embellished with 110 as the theoretical maximum score, with 10 additional points for innovation and for regional priorities.

Using LEED 2009, six geographically specific Regional Priority (RP) credits per rating system are identified (by zip code) and are worth one point each. A maximum of four RP points may be earned. 

Within the new LEED 2009 100-point system, the distribution of all points is based on the potential environmental impacts and human benefits of each credit. Impacts are defined as “the environmental or human effects of the design, construction, operation, and maintenance of a building,” such as:

  • greenhouse gas emissions
  • fossil fuel use 
  • toxins and carcinogens 
  • air and water pollutants
  • indoor environmental conditions

The point distributions in LEED 2009 systems were established using a combination of approaches, including energy modeling, life-cycle assessment1. Life-cycle assessment is an analysis of the environmental aspects and potential impacts associated with a product, process, or service. 2. The practice of quantifying and characterizing all the resource and pollution flows associated with a process or product, for the purpose of documenting its environmental impact. It is defined by the International Organization of Standardization (ISO) as "a compilation and evaluation of the inputs, outputs and the potential environmental impacts of a product system throughout its life-cycle.", and transportation analysis. USGBC now awards more points for strategies that encourage energy efficiency and carbon emission reductions. Consequently, LEED-NC 2009  Sustainable Sites (SS) and Energy and Atmosphere (EA) credits can now contribute much more toward certification than before, while total credits in the Materials and Resources (MR) and Indoor Environmental Quality (IEQ) categories are relatively less weighted.

LEED certification thresholds changed

LEED certification levels compared - LEED 2009 to LEED-NC v2.2With the change to the LEED point scale, the certification thresholds have also changed. (See table at right.)

For a “Certified” rating under LEED-NC v2.2, 26 points are needed, so each point represents 1/26 or 3.85% of certification. Under LEED 2009, 40 points are needed so each point is worth only 1/40 or 2.5%. The earning power of each individual point has been devalued in LEED 2009. In practical terms, this means that a credit that was worth one point in older rating systems, and that is still worth one point in LEED 2009, contributes less value towards certification than before.

Where will the additional 14 points needed for basic certification come from? A number of LEED 2009 credits now carry additional points, and become attractive potential targets for projects when applicable. If you’re considering switching to LEED 2009, start by assessing the likelihood of achieving these credits: 

SSc2: Development Density and Community Connectivity +4 pts
A credit typically achieved in more developed or urban sites or on campuses.

SSc4.1: Alternative Transportation: Public Transportation Access +5 pts
A credit typically achieved in more developed, urban sites or on campuses.

WEp1: Water Use Reduction: 20% Reduction
This is a new prerequisite, 

EAc1: Optimize Energy Performance +9 pts
Projects need to demonstrate improved energy performance in order to be certified under LEED 2009. Before any points are earned, you must earn LEED 2009 EAp2: Minimum Energy Performance, which calls for a 10% improvement over ASHRAE 90.1-2007. This standard is also more stringent than ASHRAE 90.1-2004, the baseline for LEED-NC 2.2. 

EAc2: Renewable Energy +4 pts  
Even with incentives, a significant economic investment is typically involved to achieve some of these points, usually with solar photovoltaics (PV), although it has now become easier to achieve at least one point under EAc2 as the threshold for one point has gone from 2.5% to 1%.  

RPc1: Regional Priority +4 pts
No additional work is necessary to earn regional priority credits. Up to four points are simply available if at least four specific credits specified for that zip code are achieved by the project. An analysis of several building types shows that many projects can expect 2–3 points here without much added effort.

System comparisons

It may be worth doing an analysis for your project, comparing LEED 2009 with older systems, side by side. An excellent free online calculator is available in the Resources section to help with this.

The consultants at the Sustainable Design Collaborative in New York did a comparison for a LEED-NC v.2.2 project that received a Gold rating with 41 Points. The project building was less than 30,000 ft2, an educational center with lodgingLodging are facilities that provide overnight accommodations to customers or guests, including hotels, motels, inns and resorts., located on a rural site in the Northeast U.S. Under LEED 2009, the project was evaluated at 49 points. However, even with the increase in total points projected to earn, it would only reach Certified level—one point shy of a Silver rating. This is an example of a specific, non-urban project scoring very differently under the two systems. 

The initial comparisons conjure up several preliminary generalities for projects:

  • Suburban and rural projects submitting to LEED 2009 will often not rate as high as with LEED-NC v.2.2 because they don’t qualify for the added points related to access to public transit. 
  • Urban projects that achieve the key Sustainable Sites credits (SSc2: Development Density and Community Connectivity and SSc4.1: Alternative Transportation—Public Transportation Access) generally experience relative equality between LEED 2009 and LEED-NC v.2.2 ratings.
  • The balance for LEED for Commercial Interiors (LEED-CI) projects, on the other hand, often skews more in favor of higher ratings under LEED 2009. The key points are for EAc1.3: Optimized Energy Performance—HVAC and  EAc2: Enhanced Commissioning.  Interior projects in urban areas often fare even better.
  • Watch out for the new water efficiency prerequisite, WEp1, which requires a 20% water use reduction compared with the typical low-flow fixture base case. This is more of a challenge than it might first appear, because the baseline for lavatory faucets changed from 2.5 gallons per minute to 0.5. This change also makes it harder to earn points in WEc3: Water Use Reduction.

Finally, be thoughtful and careful when you consider upgrading from an earlier version to LEED 2009. The presence or lack of just a few well-rewarded credits can make all the difference between a Silver or Gold rating.

Articles

The BIG Review: LEED 2009 Reference Guides Released

This article from the RealLifeLEED blog offers a detailed credit-by-credit accounting of the changes to requirements in LEED 2009.

Publications

Major Changes from LEED-NC v2.2 to LEED 2009 NC

A broad but cursory overview of changes from LEED-NC v2.2 to v2009, from USGBC.

Web Tools

LEED Online: A new and improved tool for project certification

USGBC provides this description of the enhancements to LEED Online and the new certification process, all part of LEED v3.


KEMA 2.2 to 2009 Comparison Calculator

Slick downloadable spreadsheets for LEED-NC and LEED-CS that make it easy to estimate how your project will fare in the transition to LEED 2009 (free registration required).

13 Comments

0
0
Billy Ng
Mar 15 2011
Guest
463 Thumbs Up

existing V2.2 project

Can I combine two building towers linked by a podium/mall underneath into one LEED project?
Tower 1 - registered V2.2 CS rating system, in final submission stage.
Tower 2 - just started construction which mean if registered under LEED, is going to be CS 2009.

since 2009 is more stringent than 2.2, we are afraid Tower 2 wouldhttp://www.leeduser.com/sites/all/themes/leeduser/images/form-submit.gif not meet the 2009 requirement since Tower 2 is a exact duplicate of Tower 1.

1
1
0
Tristan Roberts LEED AP BD+C, Editorial Director – LEEDuser, BuildingGreen, Inc. Mar 28 2011 LEEDuser Moderator

Billy, I would say the question of whether they can be certified under LEED 2009 depends on the relationship between the two buildings, in light of the Minimum Program Requirements. I would review those documents and post back here with your thoughts.

Post a Reply
0
0
Angelica Ospina Alvarado
Dec 14 2010
LEEDuser Member
343 Thumbs Up

Cost of upgrade

Does somebody know how much is to upgrade a project registered in LEED CS v2.0 to LEED V3? Thanks.

1
2
0
Tristan Roberts LEED AP BD+C, Editorial Director – LEEDuser, BuildingGreen, Inc. Dec 14 2010 LEEDuser Moderator

Since the free upgrade period has passed, the cost would be the same for registering a new LEED 2009 project, as it would be for upgrading. The fees are on the GBCI website -- I don't know them offhand.

2
2
0
Megan Ritchie Saffitz Director of LEED Support, U.S. Green Building Council Oct 12 2011 Guest 206 Thumbs Up

Thanks for responding Tristan. And just a quick correction: a project team that is upgrading to v2009 only needs to pay the difference between their previous registration fee and the v2009 registration fee.

Post a Reply
0
0
Diaa El-Masry Sustainable Design Manager Qatar Green Leaders
Mar 08 2010
LEEDuser Member
180 Thumbs Up

Is there a dead line to use LEED 2.2?

I just wanted to ask if there is a 'retiring' date or deadline for projects that are registered under LEED v2.2 to get certified before a certain date??? And what will happen to their application if such a date comes while not yet awarded the certificate??

Thanks,,,

1
6
0
Tristan Roberts LEED AP BD+C, Editorial Director – LEEDuser, BuildingGreen, Inc. Mar 08 2010 LEEDuser Moderator

Theoretically there could be a deadline, but so far none has been announced. Since there are so many projects (thousands) in v2.2 it seems unlikely that such a "sunset date" would be imposed anytime soon.

If such a date were imposed I imagine that they would be strongly encouraged to upgrade to v2009, rather than just falling off the map.

2
6
0
Diaa El-Masry Sustainable Design Manager, Qatar Green Leaders Mar 08 2010 LEEDuser Member 180 Thumbs Up

Thanks, Tristan for the prompt reply.
Your answer to my question was so clear...

3
6
0
Huan Pedro Oct 21 2010 Guest 50 Thumbs Up

Nice job! alot of usefull information, thank a lot! I found you by google

4
6
0
Nadav Malin USGBC LEED Faculty, President, BuildingGreen, Inc. Nov 08 2010 LEEDuser Moderator

As Tristan predicted, there is now a deadline. GBCI recently released guidelines stating that a project can be submitted in a version of the rating for us to six years after that system is no longer available for registration.

Since NC-2.2 was available for registration until June 26, 2009, the deadline for submitting under that system would be June 25, 2015.

5
6
0
Susan Di Giulio Project Manager, Zinner Consultants Mar 14 2011 LEEDuser Member 442 Thumbs Up

Very useful!
Is this deadline for construction submittal or design?

6
6
0
Tristan Roberts LEED AP BD+C, Editorial Director – LEEDuser, BuildingGreen, Inc. Mar 14 2011 LEEDuser Moderator

Susan, it's important to note that this deadline has not been officially announced—we're simply anticipating what it will be based on stated GBCI policy.

Based on the sunset date announcement for NC v2.1, the 2015 date would be the deadline for final (construction) submittal.

Post a Reply
0
0
Lauren Glasscock Sr. Sustainability Professional DNV KEMA Energy & Sustainability
Oct 13 2009
LEEDuser Expert
8681 Thumbs Up

New CIRs are not precedent setting

As I understand it, since June 26, 2009, all CIRCredit Interpretation Ruling. Used by design team members experiencing difficulties in the application of a LEED prerequisite or credit to a project. Typically, difficulties arise when specific issues are not directly addressed by LEED information/guide rulings for all rating systems including pre-LEED 2009 and current versions, will be project specific. The ruling will only apply to the project and there will not be any CIRs published on the USGBC website under the CIR database. The CIR response you receive from your CB (Certified Body) will not be applicable across other LEED systems or other projects.
You'll submit your project specific CIR through LEED Online for LEEDv2009 projects. You can get more info here at the bottom of the page: http://www.gbci.org/DisplayPage.aspx?CMSPageID=142

Post a Reply

Start a new LEED comment thread

May 26 2013